Long-Term Facilities Plan Update

July 31, 2025

Introduction

The Shaker Heights City School District is pleased to provide updates on the latest developments with various renovation projects as a part of the District’s Long-Term Master Facilities Plan. The District's commitment to enhancing the educational environment for students continues to drive these efforts.


Activating the Long-Term Master Facilities Plan has been well underway. Below are opportunities for engagement. If you have a question or comment on the facilities plan, please fill out this form. Share this newsletter with friends and neighbors in Shaker Heights! Subscribe to the facilities newsletter.

In this Message

  • Woodbury Partial Demolition Underway
  • Facilities Advisory Committee Meeting on Monday
  • Ludlow Renovation Update
An excavator tears down the pool at the former Woodbury Elementary School and there is a pile of rubble in the foreground.

Woodbury Partial Demolition Underway


Partial demolition at Woodbury began on Monday. Gilbane Building Company and AKA Construction Management started tear-down with the pool and gym. They are spraying water during the demolition to minimize dust. The contractors will move on to the wings in the coming months. The center building, which was built in 1918, will be retained and renovated. In the spring of 2026, contractors will begin work on the addition, including classrooms, an auditorium and a natatorium. The Woodbury building will reopen in Fall 2027 as the new Middle School.


Facilities Advisory Committee Meeting on Monday


The Facilities Advisory Committee (FAC) will meet on Monday, August 4. Andrew Pratt, an arborist with The Dirty Horticulturist LLC, will share information on his role as a consultant for the District, including pre-construction planning, tree risk assessments, construction tree protection oversight, and post-construction remediation. Todd Gerber of Gilbane Building Company will also attend the FAC meeting to give an update on construction at Woodbury and Ludlow.

Ludlow Renovation Update


The Ludlow renovation is progressing as planned, but past and current weather conditions continue to present challenges to the construction schedule. Restroom wall tile installation and gymnasium ductwork are complete. Grading work continues at the south side of the building for the playground. Contractors began door frame installation this week. Various other types of work are ongoing, including construction of the vestibule, painting, wood floor staining, and installation of the elevator shaft, roofing, windows, and plumbing and lighting fixtures.