Daytime Work
Daytime work occurs on weekdays between the hours of 7 a.m. and 3:30 p.m. Any work that may impact traffic flow will not occur between 7 and 9 a.m. or between 3 and 6 p.m.

Overnight Work
There is no nighttime work scheduled during for the period of October 7-18, 2019 .

Lanes Closures
From October 7-18, 2019, various single lane closures will occur on the following roads to accommodate construction:

  • South Frontage Road: between South Orange Street and College Street
  • Martin Luther King Jr. Boulevard: between Orange Street and Church Street
  • North Service Drive: at various locations locations along the service drive
  • South Service Drive: at various locations along the service drive

Tree Removal
Tree removal will occur on South Frontage Road and Martin Luther King Jr. Boulevard in the vicinity of South Orange Street.

Pedestrian Detour
A pedestrian detour is in place to accommodate construction on South Frontage Road near Church Street. The detour went into effect on Tuesday, August 13, 2019 and will last for approximately one year, until the summer of 2020. Signage will direct pedestrians to a safe route around construction; a map of the pedestrian detour is included below. Pedestrians are urged to follow the detour to stay safe as construction is in progress.

Road signage will alert drivers and pedestrians to work areas and lane closures.
Please pay attention to this signage, slow down, and stay safe!