Road, Sidewalk and Pathway Construction  
 
The City of Novi prides itself on maintaining open lines of communication and keeping community members apprised of the latest in road and  non-motorized construction projects. 

The following information is intended to provide an overview of current projects.

Please note: All completion dates are merely estimates. Projects could extend beyond those dates due to unforeseen issues with the project and inclement weather.
Oakland County Transportation  Updates


The intersection was reopened on Monday, Sept. 16. Two lanes of northbound Novi Road (right turn lane & right through lane) are still closed waiting on cure strength for a couple concrete panels that required replacement. Those lanes should open by early next week .
Estimated completion date: Road is open
RCOC is having a contractor finish the balance of concrete panel work remaining from the 2018 project which concentrated on the intersection of 12 Mile and Meadowbrook Road. The work is expected to begin at the end of September or early October, based on conversations with RCOC.
Estimated completion date: October 28, 2019

RCOC will be closing Haggerty Road on Sept. 23. Advanced warning signs and detour signs will be placed a week prior to closing, announcing the closure. The project calls for  replacing the existing culverts at two Seeley Drain crossings of Haggerty Road, north of 13 Mile Road and MacKenzie Drive. While under construction, Haggerty Road will be closed at the culvert locations.
Estimated completion date: October 20, 2019
City of Novi Projects


All of the driveways on the south side of Guilford Road have been poured and should be reopened. Driveways on the north side were being poured back this week. The first side of Bennington in Mystic Forest has been reopened and removals of the second side have started.
Estimated completion date: November 1, 2019


The base course of asphalt is down on Warrington Court and Warrington Drive, while removals are underway on  Lynwood. Crews may also head to Edinborough Lane and Inverness Court next week to begin concrete curb removals and replacements.
Estimated completion date: November 1, 2019 


The contractor will be pouring new concrete curbing along the north side of the Industrial spur road this week. The large, four-sided box culvert was placed and crews will start the process of backfilling the area. Over the next couple weeks, the contractor will concentrate on the remaining cuts and fills along the new Crescent Boulevard at Grand River Avenue as well as beginning the removals and replacements of the existing concrete at the intersection of Novi Road and Crescent Boulevard.
Estimated completion date: November 1, 2019

The contractor has closed Flint Street (gravel portion), from Grand River to Novi Road. A bulk of the earthwork and grading will take place over the next few weeks. DTE has arrived on site and is beginning to erect new power poles for the utility switch over.
Estimated completion date: December 1, 2019

The contractor has completed the milling of the existing concrete on Cabot Drive, Lewis Drive and Trans-X Drive. Over the next few days, the contractor will be repairing all of the exposed and opened joints in the milled surfaces. The first course of new asphalt pavement is going down this week or next.
Estimated completion date: October 15, 2019

The contractor has several shafts constructed for proposed sanitary manholes along Nine Mile which has choked the roadway down to one lane in several areas. Area residents and motorists need to use caution when driving in these areas. Construction of the storm sewer network at Nine Mile and Garfield Roads is now complete. Open cut sections, west of Garfield, have begun as well. 
Estimated completion date: January 27, 2020

The contractor reopened the West Park Drive bridge and closed the Meadowbrook Road bridge on Tuesday, Sept. 17. The contract has begun preventative maintenance on the under side, providing new approach concrete and epoxy coating the bridge deck on the Meadowbrook Road bridge. This work should take about two weeks. The final bridge closure is Cranbrooke Drive.
Estimated completion date: October 19, 2019

The contractor has completed paving and striping of the southbound Haggerty Road right turn lane. The 14 Mile and Haggerty intersection was fully reopened to traffic on August 23. Underground crews are on-site installing new conduit for the eventual mast arm traffic signals. Restoration will be forthcoming over the next couple weeks. Crews will also be mobilizing to the Beck Road/Pontiac Trail intersection early next week to begin installing new sidewalks, pedestrian push buttons and traffic signal conduits. After this work is complete, we will have to wait nearly 26 weeks for the delivery of the mast arms and poles.
Estimated completion date: April 1, 2020

In August 2012, Novi citizens overwhelmingly passed a road millage allowing for more than $5 million to be used in annual road and pathway investments. Funds will be used to maintain and improve neighborhood (subdivision/side streets) and major municipal roadways (mile roads, Beck Road, etc.), and to make sidewalk and pathway connections. To learn more a bout upcoming projects,  CLICK HERE.