SAN MATEO COUNTY ― Caltrans has updated the lane closure schedule on the State Route (SR) 82 El Camino Real Roadway Renewal project.
Lane closures are now scheduled from 8 a.m. to 5 p.m. on weekdays from Howard Ave. to Clark Dr. for potholing work.
- Thursday, March 12 & Friday, March 13
- Monday, March 16 - Friday, March 20
Potholing is the process of identifying utilities under the roadway to visually verify the exact depth and type of utilities present to avoid damage before paving work begins.
Full roadway closures continue from 9 a.m. to 6 p.m. each weekday from Oak Grove Ave. to Carmelita Ave. for tree removals.
- Wednesday, March11 - Friday, March 13
- Monday, March 16 - Friday, March 20
Please be aware that the discovery of Anna's Hummingbird and Oak Titmouse nests may require changes to the closure schedule at short notice.
|