Feature Project

USACE New Visitor Center & Entry Gate Patrick SFB, FL

EMR is coming to a close on the $13M Design and Construction of the main Entry Control Facility (ECF) for privately owned vehicles (POV) at Patrick Space Force Base (SFB) in Florida. This project has been in the works since the middle of June 2022. It includes a a visitor center, POV gatehouse with canopy and ID check stations, POV inspection facility and a POV over watch.

At this time, the barrel tile roof is being installed, and sod will be complete the first week of April. The wear coat of asphalt is being placed over the entire site and A1A in mid-April. We anticipate BOD for the buildings is in the first part of May. When security forces complete their network set up we will demo the existing gate and be on our way!


We would like to take a moment to thank the on-site EMR team who made this project successful:


Kyle McDorman (Sr. PM), Samantha Chuck (PM), Joe McDorman (Superintendent), Sherwood Steele (Superintendent) Sam Estok (QCM), Nick Guilbeau (SSHO / Base Access)


We know you rather be working in Mississippi, but appreciate you taking one for the team and posting up at the beach!

Images captured by our very own and highly skilled in-house photographer, Sam Estok (QCM).

EMR Family Spotlight

Last month, we received nominations for co-workers deserving of recognition. We could not narrow in on one person because each face you see below is worthy of praise.

EMR Safety Award

"Luis Marquez shows drive and determination to attain a superior and high quality finished product that will pass any inspection. His work ethic carries over to safety as well. Not only does Luis safely preform his tasks, but he also goes out of his way to watch out for the other trades on site and brings any discrepancies to the attention of the management. While addressing punch list items, Luis makes sure to ask for the proper PPE to address the task at hand, and when asked why he goes out of his way for other trades Mr. Marquez said, “to make sure everyone gets home safely to their families.” Always wearing the proper PPE, wearing harnesses on lifts, and wearing safety-belt on equipment without managerial direction are just a few of the reasons why Luis Marquez is deserving of this safety award."



- Nominated by Israel Rodriguez (EMR SSHO)

The EMR Safety Award is given to an outstanding employee or subcontractor that demonstrate best safety practices while on the job site. This month's winner receiving a gift is...


Luis Marquez

Master Carpenter

EMR, Inc.

Our daring EMR anglers recently hopped aboard "Full Draw" for a fishing experience they won't forget courtesy of Hiliner Charters..If you're looking for an exceptional deep sea fishing experience, we recommend Captain Galloway with Hiliner Charters.

New Faces


Please join us in welcoming the newest member(s) of our

EMR work family:

Nathan Eddington

QCM

Military Working Dog Kennel

Albany, Georgia

Serena Harper

QCM

CNIC 1281 Demo Facility Corpus Christi, Texas

Stephen Weech

Superintendent/QCM/SSHO

Freeport, Florida

Take 5


Bi-Monthly Project Updates

DHS Building 78 Dormitory Renovation, Ft. McClellan, Anniston AL 


We are pleased to have gained additional CO work and DHS has made their final color and material selections. The elevator shaft and corridor extension is now ready to begin brick laying. HVAC and electrical are ongoing for systems in the attic. Framing , drywall and ceilings installations are planned to be start in April. Our completion date is November 21, 2024.  

Eglin Munitions and Igloos, Eglin AFB, FL 


At Eglin Munitions and igloos, the team is working on punching out the building and still working on fire alarm testing. They are also now installing permanent fencing. All eyes are set on the end of April to close this one out.

Photo by Eglin AFB Facebook Page

AFE/TSU Bravo Camp Project, Eglin AFB, FL 


Lot of action! Slab on Grade for the main building is cemented in place (EMR). Masons (General) and Steel (Cheyenne) are finished up to the first floor. Studs and Rough-ins ongoing and gearing up to pour the Slab on Deck and move on to the second-floor masonry.


Camp Bravo is a secure site on Eglin in which no pictures are allowed to be used for marketing/advertising.

Wildcat Test Facility, Eglin AFB, FL 


Wildcat has reached the 100 percent design phase and has been submitted to the Government for review.

Shock Applied Impact Laboratory (SAIL), Eglin AFB, FL 


We are starting to pick up some steam. The EMR concrete crew has begun laying out the foundation, excavating/compacting column pads, tying rebar mats, and building forms. Site utilities are getting started with curb/gutters, sod, and pavement trailing right behind. Metal building delivery is set for mid May. Current completion date is March 10, 2025.

EMR Office, Freeport, FL


The new EMR office is coming right along with site grading being completed as well as concrete slab. Steel is here and going up. We're excited to go vertical!

DB Zone 5 CE Maintenance Shops & Storage Facilities, Tyndall AFB, FL 


Z5 CE Maintenance Shops and Storage is moving along great and potentially picking up a lot of time on the schedule. The Maintenance Shop has the greenlight to sheetrock all the walls after passing in-wall inspections; The block veneer has started on the East wall; Duct work will be starting this week and electrical is about to start roughing in their overhead homeruns. The Grounds Facility has translucent panels being installed with framing and MEP rough-in being almost complete in the administration area. The slab for the Air Filter Storage building was placed recently 2am in the morning and the structural steel contractor will be erecting the steel as soon as the slab reaches 75% strength. Current completion date is October 24, 2024.

Design and Construction of Zone 7 Munitions Storage Area, Tyndall AFB, FL


At the LDF Building we are currently installing catenary poles, the power and below grade bonding to these poles. By the end of April, we should have asphalt down and striped, with the interior completed and cleaned. As it relates to the ASES Building, we are currently installing bonding around the building, and in-wall MEP in Administration area/bathrooms/mechanical rooms. MEP is 95% complete in both bay area, and painting is ongoing. In April we will be placing hard tile in bathrooms and break rooms as well as hang the remaining interior and exterior doors to complete installation. At AGM’S 1,2,3 we have completed the precast erection and will be finishing the detailing soon as well as completing final grade at all three buildings. Hamm’s building has been erected and steel will go on later. Dissipating grounding has been installed, catenary poles are being set and asphalt binder will go down in late April. Veneer block will start after completion steel. Completion is coming up and set for mid-July.

Two Phase Design & Construction of Commercial Gate Tyndall AFB, FL


We have completed our Test and Balance and are currently conducting pre-functional checklists for commissioning. Final fencing and entrance gate to Hwy 98 are being installed. Gravity sanitary sewer is being tied in at the South side of the project, and the gate house has been cleaned. Furniture has been installed. At this time, we are currently punching out and preparing for commissioning.

Rendering

NAVFAC B147 UXS Design and Innovation Center and UXS Rapid Protoyping and Innovation Facility, Naval Support ACTY Panama City, FL


Immediately after receiving the award in late November, EMR coordinated with our Electrical Engineer and Electrical Subcontractor to procure the transformer, which originally had an estimated lead time of 877 days (~2.5 years). EMR notified NAVFAC of the long lead time during the proposal phase, which prompted them to increase the period of performance from 640 days to 900 days and issue a DPAS rating. After the transformer manufacturer received the DPAS rating letter, they were able to prioritize our order and reduce the lead time to 365 days! The project management team is coordinating with our subcontractors to complete all preconstruction submittals, submit RFI’s, and install temporary utilities and the office trailer. Current completion date is May 26, 2026.

ANG Jax F35 Flight Simulator, Jacksonville, FL


Work is progressing swiftly. MEP’s started early this month, Exterior Waterproofing is 80% complete, masonry veneer has started, Roof will be completed dried this week, catwalk is 80% installed and will be completed in two weeks and drywall has started. Completion is scheduled for the third quarter of this year.

 

NAVFAC SE DB Hurricane Sally Recovery Package 7A, Buildings 646 and 4129, NAS Pensacola, FL


HVAC piping and units are installed, and refrigerant is installed; electricians are working on new lighting and exchange of main power equipment. Window removal is scheduled for first week of April; Roofing is expected to start within 2 weeks. Current completion date is July 21, 2024.

NAVFAC NEX Renovation Project, Corry Station, Pensacola, FL


EMR is starting up one of its most recently awarded projects, NEX Renovation at Corry Station. EMR will work to renovate the NEX Main Store including the public toilet facilities, customer service area, and exterior breezeway space. A new fire pump and pre-engineered fire pump enclosure will be installed and connected to the existing building service. A bid option was awarded to remodel existing space to create a Mini-Mart area. The main store will remain open during the renovations and will require phasing of the work and coordination with store managers. We will provide a temporary restroom facility for public use while renovating the existing restrooms in the store. Currently, the temp restroom facility and job-site trailer are being set up for use during the project. The most recent completion date is set for April 17, 2025.

Rendering

NAVFAC Military Working Dog Kennel, Marine Corps Logistics Base, Albany, GA


The Field Office has been set up with site personnel working on Preconstruction submittals & onboarding subcontractors. We will start sitework within the month of April. Following that will be plans to establish the dog kennel building pad for the foundation crew. The current completion date is April 29, 2025.

Munition Storage Area Facilities, Barksdale AFB, LA


All work is compete and EMR is waitng on the first report to close this one out. Great job team!

USACE Aeromedical Evacuation Training Facility, Keesler AFB, Biloxi, MS


The work over at the new Aeromedical Building site is off to a great start. We have passed our proof roll inspection on existing soil and are beginning to build the building pad. Trucks are rolling in and dirt is being spread - it’s a good day! We have installed the underground piping for the gas, sanitary sewer, and communications, leading up to the building 90% complete. We have rerouted an 8 inch water main around the building pad, tested it, and have it back in service. Geopier will be on site next to install 168 pires the first week in April. The skies are blue, moral is up, and all is well!

NAVFAC Cryogenics Facility, Beaufort, SC


The metal studs and wall rough ins are complete over in Beaufort, and FL crane is starting to install drywall in the equipment rooms and the admin area. Outside, the sanitary sewer and fire hydrant legs are currently being installed. We expect to start on final grades and base in the middle of April. This $11M project is estimated to be complete by November 2024.

NAVFAC Demolish B760 and MWR Facilities, Naval Support Activity Mid-South, TN


The recently awarded $4M project in Tennessee is in its beginning phases. The job trailer has been mobilized and demolition should begin in the next 30 to 45 days. Stay tuned for more information as we get this one going!

NAVFAC CNIC 1281 Demo Facility, Corpus Christi, TX


The scope of this project includes the demolition of an Unaccompanied Housing Facility that is made up of a central, single story mess wing and six wings, each three stories. Demolition of the housing facility includes all foundations, walkways, canopies, staircases, and associated appurtenances (i.e., four nearby gazebos, four parking lots, a tennis/playing court, heating plant, AC plant and utilities). Work includes some hazardous material handling and incidental related work. The project management team is coordinating with our subcontractors to complete all preconstruction submittals, submit RFI’s, and install temporary utilities and the office trailer. The current completion date on this one is June 2025.

Happy Birthday!


Apr 1 - Andy Jorgensen, Tyndall AFB, PL

Apr 1 - Serena Harper, Corpus Christi, TX

Apr 15 - Tom Dorsey, Panama City, FL

Apr 16 - Matt Jones, Albany, GA

Apr 19 - Lisa McDorman, Corporate Office, FL

Happy Anniversary!


6 years - Lisa McDorman, Corporate Office, FL

1 year - Virgil Henley, Eglin AFB, FL

EMR Bids

Awaiting Notification

USACE Phase 1 DB and Construction, IDIQ MATOC DHA, Central Region

USACE Phase 1 Small Business Small Project DB MATOC, Savannah District’s Military AOR

USACE Phase 1 Design Build GC MATOC, New Orleans District

NAVFAC IDIQ MACC for General Construction Primarily in the Hampton Roads AOR, VA

Okaloosa County Baggage Claim Expansion Destin Fort Walton Beach Airport, FL 

NAVFAC Medical Addition and Renovation B4560, Barksdale AFB, LA

NAVFAC Cyber Processing Facility, Keesler AFB, MS

Currently Bidding

USACE Airman Leadership School Facility, Eglin AFB, FL

Inspiration


Lee McBride

EMR Corporate Chaplain | [email protected]

EMR Mission Statement


“Attract, retain and develop talented employees who share our vision; understand and serve our customers through partnership and sound project management practices; give back to our community, our country and our world; encourage and embody the entrepreneurial spirit; and endeavor always to make our best even better.” 

4566 Hwy 20 E, Suite 204

Niceville, FL 32578

(850) 897-0210

Suggestions or Comments?

Please email [email protected]

LinkedIn