Aug. 18, 2021 Construction Update
- Milling and paving activities will begin as part of intersection widening. This work is scheduled during overnight hours to reduce impacts to travelers during the day.
- New signal poles will be set into place after paving is complete. Existing signal bases will be demolished and removed.
- Other construction including curb and sidewalk upgrades, electrical, and landscaping work continues.
- Thank you for your patience during this important project!
Nighttime lane closures remain in place. Motorists should plan for:
- Increased truck traffic in the area.
- Increased number of crews and noise - including backup alarms.
- Bright lights throughout the work zone.
The project team encourages everyone traveling traveling through the intersection to slow down and watch for orange barrels, cones, and signage indicating traffic shifts in the work zone. Pedestrian and cyclists are encouraged to follow all posted signs