Crane Lift - LUXBAR
LUXBAR has hired Gatwood Crane to lift roof top units on October 21, from 8am to 11am. They will close Bellevue, from Rush to the first alley east thereof.
Residential Lighting Project Notice: Huron, from Michigan to Fairbanks
The Chicago Department of Transportation will be installing new street lights on East Huron Street, between North Michigan Avenue and North Fairbanks Court. Construction is tentatively scheduled to begin the week of October 21, 2024, pending clearance from and coordination with existing utilities, current work schedule fluctuations, and weather permitting. John Burns Construction is the contractor for this project and Stanley Consultants is providing resident engineering services for the Chicago Department of Transportation.
The work will include the installation of foundations, boring of underground conduits, cable pulling, the installation of new residential lighting poles with piggyback lights, LED Smart Lighting luminaires, and the restoration of concrete sidewalks and parkways disturbed by the construction. The existing light poles will be removed once the new lighting system is functioning properly.
During construction, temporary “No Parking” signs will be periodically installed as required for each activity listed above so that work may be performed safely. These temporary signs will restrict parking during working hours, and residents can park normally after the posted hours and overnight, and usually all day on weekends.
The project is expected to be completed by December 2024.
172 W Adams Mechanical Equipment Work
Standard Cartage Company was hired by 172 W Adams to replace/service mechanical parts in the building. They need to close Marble Place, between Wells and LaSalle during the work to lift equipment in and out of the building.
Work will occur Monday, October 21 to Friday, October 25, from 8am to 5pm. The alley will reopen at 5pm each day
Upcoming Work - Chicago/Halsted Viaduct Repairs
CDOT crews are scheduled to perform bridge repairs at the Chicago/Halsted Viaduct. Please see details below:
Scope of Work:
The project consists of performing the following repairs: Beam Repairs at the SW corner of the viaduct.
Construction Schedule:
Thursday, 08/29/2024 - Thursday, 9/19/2024
Traffic Impact during Construction:
- A single Southbound vehicular lane closure on Halsted St. from the Chicago River to approximately 75ft south of Chicago Ave.
- A single Eastbound vehicular lane closure on Chicago Ave. from N. Green St. to S. Halsted St.
Helicopter Lift - 800 N Michigan Avenue
On Saturday, October 26, from 9am to 11am, there will be a crane lift at 800 N Michigan Avenue. During the lift, the following will be closed to pedestrians and vehicular traffic:
- Michigan, from Chicago to Chestnut
- Chicago, from Michigan to Rush
- Pearson, from Michigan to Rush
Filming
Tortoise Supper Club
On Monday, October 21, a filming for an independent film, "The Up & Comer", will take place inside the Tortoise Supper Club at 350 N State Street. Parking will be prohibited at the following locations:
- Both Sides of Kinzie St from State St to Lower Wabash
- East Side of State St from Kinzie St south to Chicago River
- Both Sides of Lower Wabash from Kinzie St to Hubbard St
Pin & Link Project on Randolph and Columbus
CDOT crews are scheduled to perform steel work and bridge expansion joint rehab along Randolph Street, Columbus Drive, and Stetson Avenue. Please see details below:
General Construction Schedule:
7:00 am - 3:30 pm, Monday - Friday; with the occasional extension to 5:30 pm as needed.
Scope of Work and Access Impacts During Construction:
In general, one lane of travel will be open at all times along each roadway, level, and direction. Access along sidewalks will remain open with detours around the work areas.
Week of 10/21 thru 10/25:
- Randolph Street Scope:
- Stetson to Columbus - Work continuing along the south sidewalk and moving to the north sidewalk mid-week. Work at bridge expansion joints.
- Access Impacts:
- Prudential building parking garage access impacts on lower Randolph at Stetson.
- Columbus Drive Scope:
- Intermediate Level at north side of Randolph St. Intersection - Tarps setup to clean bridge steel.
- Intermediate Level Randolph to Lake St. - Work along both east and west sidewalks.
- Access Impacts:
- Intermediate median lanes closure through 10/22. Closure shifting to northbound right lane mid-week.
- Stetson Avenue Scope:
- Wacker to South Water St. - Expansion joint removals in sidewalk and roadway anticipated start 10/25
- Access Impacts: Southbound Stetson drop-off lane reductions
Bridge Repair
CDOT crews are scheduled to perform bridge repairs (Gusset Plate & Sidewalk Bracket repairs) at the Grand Avenue Bridge over the N Branch of the Chicago River on Monday, October 21st - Friday, December 6th.
Traffic Impact during Construction: Daily closure will be set up 7am - 4 pm
Set up includes the following:
- One sidewalk will remain open for pedestrians traffic during construction
- WB and EB will be partially closed still allowing two-way traffic.
Added Bus Stops
Due to the Expanded Outdoor Dining program, the following bus stops will be implemented, effective on Friday, May 24, 2024, at 3:00 pm until Thursday, October 31, 2024 or completion.
Clark at Kinzie (southbound, nearside)—Temporary bus stop elimination
Stop ID Number: 1861
Route Stopping: #22 – Clark
LaSalle at Grand (southbound, farside)—Temporary bus stop route added onto existing bus stop
Stop ID Number: 4961
Route Stopping: #22– Clark, #156 - LaSalle
LaSalle at Hubbard (southbound, farside)—Temporary bus stop route added onto existing bus stop
Stop ID Number: 4962
Route Stopping: #22– Clark, #156 - LaSalle
LaSalle at 320 North (southbound, farside)—Temporary bus stop route added onto existing bus stop
Stop ID Number: 4963
Route Stopping: #22– Clark, #156 - LaSalle
State & Lake Utility Relocations
Utility companies began relocating utilities in advance of the State and Lake CTA project. Train services will not be disrupted during utility relocations.
At least 1 lane of traffic will remain open (1 lane each direction on State St) at all times, but other driving and parking lanes may be closed.
Construction equipment and materials will be stored on the street, including during time periods between active work. Work will primarily occur 9:00 AM to 4:00 PM on weekdays and 8:00 AM to 8:00 PM on Saturdays, but there will be limited work during nights. Utility companies are aware of and required to abide by the Chicago noise ordinance, which limits noisy work during overnight hours.
Kennedy Expressway Bridge Rehabilitation
In 2023, IDOT began rehabilitating the Kennedy Expressway (Interstate 90/94), from the Edens Expressway (I-94) junction to Ohio Street.
The estimated $150 million project consists of rehabilitating 36 bridges and the Reversible Lane Access Control system, replacing overhead sign structures, installing new signage and modernized LED lights, pavement patching, and structural painting. Additionally, Hubbard’s Cave, from Grand Avenue to Wayman Street, will be painted and new LED lighting installed.
The work will take place over three consecutive construction seasons, broken down into the following stages:
-
2023 – Inbound Kennedy: Click here for stage 1 fact sheet.
-
2024 – Reversible Express Lanes: Click here for stage 2 fact sheet.
-
2025 – Outbound Kennedy: Click here for stage 3 fact sheet.
The Kennedy Expressway officially opened in November 1960, with the last major rehabilitation completed in 1994. The project will improve safety, traffic flow and reliability for the more than 275,000 motorists who use the expressway each day.
Click here for a project overview.
Click here for a FAQ
Click here to see photos and videos of the project.
|