Hello
Early Voting polling locations and times
There are plenty of the important items on the ballot this year! Make sure to get out and vote! For more information on the upcoming election visit https://elections.mctx.org/ .
Download the P3 Works app today!
Want weather alerts and high water locations during a severe weather event? (see below for an example of a push notification)? Download the P3 Works app! You can also use the P3 Works mobile application to submit a work order today! We also have created an online desktop version as well that you can access straight from your desktop PC. Click the link below to submit a work order today!
Road Project Updates
Gosling Road construction project still on schedule to start this year

Harris County is working to schedule a pre-construction meeting prior to the start of the Gosling Road widening and bridge project over Spring Creek in The Woodlands.

The project is a joint effort, with Montgomery County Precinct 3 Commissioner James Noack’s office funding $4 million and Harris County Precinct 4 Commissioner Jack Cagle’s office funding the remaining $4.2 million of the $8.2 million project.

The project falls within the boundaries of The Woodlands Township, which benefits from the costs being spread among property taxpayers across Montgomery and Harris counties instead of falling solely on the shoulders of The Woodlands property owners if it were a city.

In addition to the two precincts partnering on the Gosling Road project, The Howard Hughes Corporation donated land for additional detention areas to meet drainage requirements.

Scope of project: The project will widen Gosling Road to a full four-lane boulevard between Creekside Forest Drive in Harris County and Gatewood Reserve Lane on the north side of the project in Montgomery County. It will result in two 12-foot lanes in each direction. The road pavement will be 10-inch jointed reinforced concrete with 8-inch stabilized subgrade.

The widening includes the construction of a 1,817-foot bridge crossing over Spring Creek for the two new southbound lanes. The existing bridge lanes will become the two northbound lanes. The sidewalk and existing 8-foot shoulder along the northbound side will remain. The new southbound bridge will have a safety shoulder for motorists to access in case of vehicle breakdown.

Northbound Gosling Road at the intersection with Creekside Forest Drive will be restriped to allow two through lanes of traffic and a left-turn lane. Some minor adjustments will be made to the emergency traffic signal at the intersection with The Woodlands Fire Station No. 8 to account for the new southbound lanes.

The additional detention will be constructed on the north side of the project and drain into Spring Creek.

Harris County awarded the contract in July to NBG Constructors.

The construction project, once started, is estimated to take 14-15 months to complete.
Turn-lane work, tie-in paving continues on Rayford Road-Birnham Woods project

Project Update: Contractor D&W has been working on the concrete tie-ins along Rayford Road at the far west and east ends of the project. Concrete was poured earlier this week at the west end, while excavation has started on the east-end tie-in approaching Birnham Woods Drive. D&W also will continue pavement work at the Birnham Woods Rayford Road intersection for additional traffic lanes.

In addition, D&W Contractors has removed some pavement from the existing bridge and is working to construct the left-turn lane on the new bridge from Rayford Road to Spring Trails Park Drive.

As part of the ongoing work, eastbound traffic recently was shifted to the new lanes. Motorists are reminded to use caution through the work zone and pay attention to signage. Power was turned on for the new traffic signal at Rayford Road and Harmony Woods/Allegro Bend Boulevard. That intersection signal will remain in flash as a four-way stop during this phase of the project.

Construction of the traffic signals at Rayford Road and Harmony Creek/Harmony Forest Boulevard also has been completed and power should be turned on soon.

Following construction of the left-turn lane on the new bridge, traffic signals will be completed at the Rayford Road-Spring Trails Park intersection.
Construction of traffic signals at the Rayford Road-Birnham Woods Drive intersection will commence once the contractor makes more progress on widening that intersection.

When the Rayford Road-Birman Woods Drive project is completed, traffic signals will replace all-way stops at these intersections:

  • Rayford Road and Birnham Woods Drive
  • Rayford Road and Harmony Woods/Allegro Bend Boulevard
  • Rayford Road and Spring Trails Park Drive
  • Rayford Road and Harmony Creek/Harmony Forest Boulevard

Pedestrian signal poles and crosswalks will be included as part of the intersection signalization.

Scope of project: The project will widen Rayford Road to four lanes from approximately 40 feet east of Waterbend Cove to approximately 400 feet east of Birnham Woods Drive. A new concrete roadway will be constructed on the south side of the existing Rayford Road lanes to create the two new eastbound lanes. The existing road will be for the two westbound lanes along that stretch. Left-turn lanes also will be added for eastbound and westbound traffic at most of the intersections.

The construction includes an additional bridge for eastbound Rayford Road traffic just east of Spring Trails Park Drive.

The project also involves constructing traffic signals at the Rayford Road intersections with Birnham Woods, Harmony Woods/Allegro Bend, Spring Trails Park Drive and Harmony Creek/Harmony Forest. Birnham Woods Drive also will be widened to four lanes from approximately 600 feet north of Rayford Road to approximately 600 feet south of Rayford Road. All four Rayford Road-Birnham Woods Drive intersection approaches will have a dedicated left-turn lane.

Contract length: The Rayford Road-Birnham Woods Drive widening, intersection improvement and signalization project started at the end of October 2020. It is a 360-calendar day contract to complete the job.
Bridge deck poured, concrete pavement progresses Kuykendahl Road widening project


Project Update: Contractor WadeCon LLC recently completed the concrete pour of the bridge deck over Bear Branch along the Kuykendahl Road widening project.

The contractor continues to make main-lane progress along the approximately 1.5-mile-long project, with more than 70 percent of the concrete pavement completed.

Scope of project: The project will widen Kuykendahl Road from a two-lane half boulevard to a four-lane full boulevard from Lake Woodlands Drive to Research Forest Drive.

Project design includes construction of two 12-foot-wide northbound vehicle lanes from north of Lake Woodlands Drive to south of Bay Branch Drive with an 8-foot-wide outside shoulder along the new northbound lanes. There will be a new bridge constructed over Bear Branch for the northbound lanes that have the shoulder as well as a walkway, mirroring the existing bridge.

The two existing lanes will become the southbound lanes once construction is completed.


Contract: The project started in January 2021 and is a 365-calendar day contract to complete the job.
Striping Projects

  • Dry Creek - Completed
  • Grogan's Point Road - Ongoing
  • Falls Lake Drive - Ongoing
  • Birnham Woods Drive (From Elan Boulevard heading north) - Completed
Bridge Painting

  • Caraquet bridge (In Imperial Oaks) - Ongoing
  • Bridge rail and walkway are being repainted, and fencing replaced.
Asphalt Projects
Dry Creek
  • Asphalt/road repair and replacement on Dry Creek (Completed)
Robinson Road
  • Robinson Road (west of Imperial Oaks Boulevard/Willow Creek Park Intersection) approximately 300 feet of asphalt pavement will be replaced along the two-lane road in the near future.
Precinct 3 crews hard at work!
Between September 15 and October 13, 2021, Precinct 3 crews opened and completed 630 work orders. These are your tax dollars hard at work.
County Closures
Veterans Day
Montgomery County Offices will be closed, Thursday, Nov. 11, in observance of Veterans Day.
american-flag-wavy.jpg
Precinct 3
Precinct 3 Projects
Now on the Precinct 3 website, you can see the breakdown of every road bond project, including the estimated cost, engineering firm and progress. We also added information for other major projects and road improvements, such as striping.
What do we do?
How does Precinct 3 serve you? We put together a video to show you all of the services provided by Precinct 3.
James Noack
Commissioner Precinct 3
Montgomery County
1130 Pruitt Rd
Spring, Texas 77380
 281-367-3977