Beginning Thursday, Oct. 13, crews will:
-
Haul in and place topsoil on the south side of East Flamingo Avenue to promote growth of new vegetation in the spring.
-
Lay down subgrade and base layers to support the new road surface.
Once these activities are complete, crews will begin asphalt paving. ITD expects paving on East Flamingo Avenue to conclude in December.
|