SPECIAL ANNOUNCEMENT: Major construction activities to begin on the Exit 16 Diverging Diamond Interchange (DDI) Project on Sunday, September 14, at 7 PM. Construction activities will take place during nighttime hours (7 PM to 6 AM), Sunday through Friday, and during daytime hours (6 AM to 3 PM), Monday through Friday.


Work throughout the fall will focus on traffic signal work at the intersection of Tigan Street and Main Street in Winooski (U.S. Routes 2/7), ledge removal to widen U.S. 2/7 (including drilling and blasting), and the construction of new drainage and stormwater infrastructure.



Motorists should expect significant delays when traveling through the work zone and along adjacent roadways. Please plan ahead, leaving plenty of additional time to get to and from your destination. Whenever possible, consider alternate routes or other forms of transportation such as carpooling, ridesharing, transit, biking, or walking.

TRAFFIC IMPACT AND DURATION: From Sunday, September 14, through Friday, September 19, between the hours of 7 PM and 6 AM, crews will be working on U.S. 2/7 near the Highpoint Center driveway under lane closures and lane reductions. This work may require lane closures within the Highpoint Center driveway. Access will be maintained.


From Monday, September 15, through Friday, September 19, between 6 AM and 3 PM, crews will be working on U.S. 2/7 between South Park Drive and Mountain View Drive under lane closures and lane reductions.


Motorists should expect significant delays and are encouraged to seek alternate routes or plan extra travel time. Drivers should slow down, use caution, and follow flaggers and road signs.

CONSTRUCTION ACTIVITIES: Crews will begin removing ledge and preparing for future blasting operations along U.S. 2/7 near Mountain View Drive and begin installing drainage and stormwater infrastructure along U.S. 2/7 between South Park Drive and Mountain View Drive.

LOCATION: U.S. Routes 2/7 in Colchester starting at the Winooski town line and continuing north for 1.05 miles to Sunderland Woods Road.

PROJECT COMPLETION: Contract 1 Fall 2023

Contract 2 Summer 2027

Nearby Construction Project Highlights

VTrans Colchester Exit 17 Project

  • Project Area: I-89 Exit 17, U.S. 7 between the Shell Gas Station and Wiley Road, U.S. 2 between Chimney Corner and Jasper Mine Road
  • Next week: Crews will construct Exit 17 acceleration and deceleration lanes and continue with existing U.S. 2 bridge and roadway demolition and removal.
  • Traffic Impacts: Monday – Friday, 6 AM – 7 PM | I-89 northbound and southbound single-lane closures near Exit 17 during off-peak hours. U.S. 2 lane closures and intermittent alternating one-way traffic.
  • Construction: Spring 2024 – Summer 2026
  • Project Website


City of Winooski Main Street Revitalization Project

  • Project Area: Main Street in Winooski, between the railroad bridge near Maple Street and the Colchester town line near Checkerbay Carwash
  • Next week: Crews will continue with traffic signal upgrades, sidewalk/brick paver installation, road reconstruction, and underground utility and stormwater work.
  • Traffic Impacts: Monday – Friday, 7 AM to 7 PM | Main Street restricted to northbound traffic only; Southbound traffic detoured to Tigan Street and Weaver Street. Periodic side street closures at Main Street intersection.
  • Construction: Spring 2024 – Summer 2026
  • Project website



Diamond Interchange Comes to Vermont Educational Video

This video provides an overview of the Exit 16 DDI project, discusses the benefits of the Diverging Diamond Interchange design, and demonstrates how drivers, cyclists and pedestrians will navigate the new traffic pattern coming to Colchester, VT.


Watch now!

Translated Materials

VTrans is committed to providing a comprehensive and robust communications and public outreach program as part of this project. 


The project website has been upgraded to include a translation feature with the ability to automatically translate website content into 11 languages. 


In addition, the website is now home to a translated materials tab which includes several frequently asked questions and answers that have been translated into 11 languages with help from trained interpreters and translators from AALV in Burlington, Vermont. 


View now!



CONTACT US:


Project Hotline: 802-595-4399

Project email address: info@Exit16DDI.vtransprojects.vermont.gov

Project Website

Vermont Agency of Transportation | https://vtrans.vermont.gov/
Facebook  Twitter  Instagram