Madison Dam (Lake Moraine) Rehabilitation Project
Dam Project and Drawdown: Please share any thoughts, questions, or concerns you have after the Canal Corp meetings. The Board of Directors takes your concerns seriously and will communicate them with the Canal Corporation, as appropriate. You can write to Nancy Ries at nries@colgate.edu or by phone or text: 315-750-0007, or communicate to any other Board member.
Information from the Canal Corp meeting on 10/8/2025 regarding the Dam Construction Project
Upcoming Timeline -
2026 Drawdown to begin in "Spring" (mid-March) through "Late Spring" (the end of May or beginning of June), the Causeway will have a cofferdam on the North side to hold water 4' higher than the lower basin, Build cofferdam tight to the current Spillway, and construction of major components will follow
2027 Construction of major components will continue
2028 Lake refill will begin in January, clean up and restoration. It is expected to take 3-6 months for the lake to fill.
Canal Corp can provide informational guidance to residents that expect to experience an issue with their water. They will not be providing water.
Under Health Department guidelines, shallow well-water is termed "ground water under direct influence of surface water" and not appropriate for human consumption as it can contain pathogens. If the quality of your water changes with the fluctuation of the surface water, you need to contact the Madison County Health Dept.
They can also provide tools for shoreline issues and access to islands. Please contact them.
Canal Corp is not planning any road closures for Spillway Road and East Lake Road. There may be short, temporary closures for deliveries.
Madison County is planning culvert replacements in 2026. They will replace a culvert on East Lake Rd and then the Causeway culvert. There will be road closures involved with these replacements. They also have a permit to dredge the lake between East Lake Road and Snake Island.
Expected Phases:
2026--Site preparation, Current valve house dismantled, Cofferdams built, Low level Spillway will be built with 4-24" pipe openings, Block the Oldest Spillway, Improve the left embankment
2027--Build Spillway cofferdam, Demo current Spillway, Build new Spillway, Create grading and drainage on the right embankment, Install Upstream Slope Buttressing which won't be seen (large rip rap on water side for structural stability)
2028--Begin lake re-fill, Wrap up management, Valve house reconstruction, Build bridge over new Spillway, Build several access roads, Various improvements, Complete restoration
The hours of work will be 7 a.m. to 5 p.m. The contractor can ask for overtime hours and they will be considered. Work will NOT be 24 hours a day.
The boat launch will be temporarily extended. The DEC will also add additional concrete to the end of the permanent boat launch.
Most of the current earthen dam will remain and won't be removed. Additional material and topsoil will be added. The current rip rap on the water side of the dam will remain during and after the project.
The construction company will have penalties for not completing phases on time.
The drained lakebed condition is expected to be mucky in some areas which will take longer to dry out, Cobble areas which would dry faster, Slimy in some areas until they dry out, Smelly at the start, which will subside as the decaying vegetation dries out, Land bearing vegetation will quickly take over the dry lakebed.
According to the DEC, the fish are expected to be fine. The small fish will be eaten. Their natural reproduction will be affected for the 2-year project but will be ok after the water comes back. There will be plenty of fish to reproduce after the 2-year project.
Milfoil won't survive out of the water. Other (land) vegetation will take over. When the water comes back hopefully native plants will come back. There isn't a way to introduce native plants to bring them back.
Docks can be extended to the water during drawdown. Army Corps of Engineers and DEC have no issues with that.
The labyrinth design of the Spillway adds face without adding length and controls and shapes the water exiting over the spillway. The different sides have slightly different heights, preventing a single-stream rush of water over the spillway, preserving the whole structure. It also allows for higher drainage volume than a straight exit.
Once the project is complete, the upper 10' of the lake water level will be regulated by a gate which will help improve Winter water levels. The gate can be set at a specific level to maintain water level.
The Canal Corp website will be updated with information from the meeting, real time water level grid, and a map to calculate distance from your property to the waterline at 10' drawdown.
https://www.canals.ny.gov/Operations-and-Public-Projects/Project-Work/Madison-Reservoir-Dam-Rehab
Jackie's contact information is:
Jackie Schillinger
Senior Communications Strategy Manager – Canals