The Phase One A work will continue to accelerate this week, including…
- beginning the installation of the altar and ambo,
- preparing the platform for the new tabernacle stand and wall installation
- reworking the confessionals to create the Baptistry (1)
- starting the finish work on the Marist Chapel of St. Peter Chanel
We are currently tracking to reach the goal of completing Phase One A by Advent. For the next several weeks an additional email will include updates and photos to record our progress.
|