G.O. Bond: 41 Street Corridor Revitalization Project

Notice Date: November 14, 2024

 

Project Update

The City of Miami Beach will provide project updates to the G.O. Bond Oversight Committee (GOBOC) today, November 14, 2024. A comprehensive presentation to the City Commission will follow on November 20, 2024, where the Administration will share project updates, including additional scope requested by the community and recommendations from the Design Review Board (DRB). The goal of this meeting is to obtain design approval and guidance on the project's next steps.

Timeline

The 60% design documents are being finalized and will be submitted for review by the Florida Department of Transportation (FDOT). The city anticipates starting 90% design construction documents in April 2025.


The project is expected to commence in Spring 2026 and will take approximately two years to complete. This timeline accounts for the concurrent execution of a critical water main infrastructure project, which will be carried out simultaneously with this Capital Improvements Project (CIP) to optimize efficiency and minimize disruptions.

Contact 

For more information, please contact Neighborhood Affairs Division Liaison Heather M. Leslie at heather@hmlpublicoutreach.com.

To learn more about the city’s projects and innovative initiatives, visit www.miamibeachfl.gov/NAD.


To request this material in alternate format, sign language interpreter (5-day notice required), information on access for persons with disabilities, and/or any accommodation to review any document or participate in any city-sponsored proceedings, call 305.604.2ADA (2232) (voice), select 1 (English) or 2 (Spanish) and leave a message with your request. TTY users may call via 711 (Florida Relay Service). You can also make requests online at www.miamibeachfl.gov/ada by selecting ADA request.

Facebook  X  Instagram