Facade Repairs
G3 was engaged by this Lakeview Condominium Association to investigate water infiltration issues. Investigative openings were made after a series of prototype drops to determine where the water was entering the building from and what repairs would be needed to prevent that from happening. G3 then managed the project repairs which included:
- steel lintel replacement
- flashing installation
- cracked brick/sill replacement
- tuckpointing
- sealant replacement throughout all elevations of the building
G3 worked with the masonry contractor to develop the project schedule and phasing plan to complete the project in one year. The project started the first week in March 2020 and was complete by the first week in October 2020. The building was split into 13 drops and had 5 swing stages going at a time.
With cost savings generated by the G3 team, $65,000 was returned to the Association.