Planned Pre-Construction Work in Cambridge
Our contractor crews continued with field tests or "test pits" along the proposed GCEP routes to further engineering efforts. Here is a summary of progress in Cambridge from activities performed this month and upcoming:
Field Tests:
- Intersection of Portland Street Broadway (Complete)
- Intersection of Cardinal Medeiros Avenue and Hampshire Street (Upcoming)
Geo-technical Borings:
- Broadway between Galielo Way and Third Street (Complete)
- Third Street between Broadway and Linsky Way (Complete)
- Second Street between Linsky Way and Athenaeum Street (Ongoing)
- Ames Street between Broadway and Amherst Street (Ongoing)
- Vassar Street between Main Street and Waverly Street (Upcoming)
|