MAY

31

The contractor anticipates performing a traffic shift next week (eliminating the left turn lane) on 13 Mile Road, between Meadowbrook Road and M-5, as they begin to install the new water main on the south side of the roadway.

13 MILE ROAD

BETWEEN M-5 & MEADOWBROOK ROAD

The contractor has begun excavating for a valve vault on the north side of 13 Mile Road at M-5.


On Monday, June 5th, the contractor will begin a traffic shift, asphalt removal and water main installation on 13 Mile. Two-way traffic will be maintained, and turn movements will not be restricted; however, the left turn lane will be eliminated throughout construction.


The Novi Police and Fire Departments are aware of the upcoming construction and will provide police presence or flag control onsite during peak traffic hours. Police presence or flag control is anticipated to begin Monday and continue weekdays from 7-10 am and 3-6 pm.


A three-day closure at M-5 is anticipated to take place June 14-16. The posted detour will be M-5 to 14 Mile Road to Novi Road to 13 Mile Road, and vice versa.


If, for any unforeseen circumstances, the closure needs to be extended past these three days, we will communicate that via this email.


After the three-day closure of 13 Mile Road, the contractor will begin the installation of the water pipe on the south side of 13 Mile Road. At this time, 13 Mile Road will be partially reopened for use, and the lane shift on 13 Mile Road will continue to be in effect.


Fox Run residents may want to consider turning right out of the community to avoid the potential for traffic backups.


GLWA anticipates road work completion on this portion of the project in late summer.

MEADOWBROOK ROAD

The contractor is still on schedule to complete road work on Meadowbrook north of 12 Mile Road in October 2023.


The contractor has completed the micro-pile installation and continues installing the new sanitary sewer. Residents living in the Beacon Hill subdivision and north of Hummingdale Circle should continue to go south to 12 Mile Road. Street sweeping will continue one to two times per week.


While Meadowbrook Road remains closed south of Brownstone Drive, access to the Crosspointe Meadows Church and Meadowbrook Elementary continues to be maintained.


Residents of Meadowbrook Townhomes, Tollgate Woods, and Tollgate Ravines should avoid Meadowbrook Road and access the neighborhoods from 13 Mile Road.

THANK YOU

Again, we apologize for the inconvenience. We truly appreciate your patience and understanding and will work to be as accommodating as possible.


Please forward this to anyone who might want or need to be kept informed of the water main construction impacting 13 Mile and Meadowbrook Roads. Those wishing to join the distribution list can simply CLICK HERE to sign up.