The contractor has begun excavating for a valve vault on the north side of 13 Mile Road at M-5.
On Monday, June 5th, the contractor will begin a traffic shift, asphalt removal and water main installation on 13 Mile. Two-way traffic will be maintained, and turn movements will not be restricted; however, the left turn lane will be eliminated throughout construction.
The Novi Police and Fire Departments are aware of the upcoming construction and will provide police presence or flag control onsite during peak traffic hours. Police presence or flag control is anticipated to begin Monday and continue weekdays from 7-10 am and 3-6 pm.
A three-day closure at M-5 is anticipated to take place June 14-16. The posted detour will be M-5 to 14 Mile Road to Novi Road to 13 Mile Road, and vice versa.
If, for any unforeseen circumstances, the closure needs to be extended past these three days, we will communicate that via this email.
After the three-day closure of 13 Mile Road, the contractor will begin the installation of the water pipe on the south side of 13 Mile Road. At this time, 13 Mile Road will be partially reopened for use, and the lane shift on 13 Mile Road will continue to be in effect.
Fox Run residents may want to consider turning right out of the community to avoid the potential for traffic backups.
GLWA anticipates road work completion on this portion of the project in late summer.
|