GPL & NCAM Redevelopment Project | August 2021
GPL & NCAM starting to take shape above ground
Construction continues on schedule
Aerial of GPL & NCAM construction site in July 2021
The new Golden Plough Lodge and Northumberland County Archives & Museum facility on Courthouse Road in Cobourg is starting to take shape above ground as construction work progresses on schedule for completion by late 2022.

While most of the work completed since the launch of construction in December 2020 has been hidden underground, progress is now visible at the site as the team has begun forming footings and walls above ground. The structure will continue to take shape throughout the year as the construction focus shifts to the superstructure in the fall.

Construction highlights to date
  • 1,758 cubic meters of concrete poured
  • 290 meters of sanitary main installed
  • Continuation of footings and walls for north and south buildings
  • 9850 cubic yards of engineered fill delivered to site
  • 1328 geopiers (columns of uniformly graded and compacted stone) installed to strengthen the ground for construction

Watch the progress
For a bird's-eye view of the construction progress from May to July 2021, view our August 2021 GPL & NCAM Redevelopment Construction Update video by visiting Northumberland.ca/GPL_NCAM.
KEY MILESTONES
Completed - circle with checkmark
Design Development
June 2018 to October 2020
Completed - circle with checkmark
Site Plan and Tender
October to November 2020
In progress - filled in circle
Construction
December 2020 to summer 2022
Not completed - circle with no checkmark
GPL Move-In
Fall 2022
Not completed - circle with no checkmark
NCAM Move-In
Fall/winter 2022
CURRENT PHASE
Earthwork
Ongoing throughout construction
Foundations
Spring to summer 2021
Site service connections
April to fall 2021
NEXT STEPS
Superstructure (above ground) construction
Fall 2021
Looking to provide feedback, get more information or ask a question?
Email us at [email protected]