|
The remaining utility work includes Georgia Power and Comcast relocation of overhead lines south of Old Spring House Lane. AT&T must also relocate overhead and underground lines throughout the construction zone.
Based on the progress of the utility work, the city’s contractor, Lewallen Construction, has been able to begin work on the north end of the project (primarily between Kent Ave and N. Shallowford Rd). This includes new curb work, portions of the new storm drain system, and segments of the sidewalk in the northwest quadrant. The contractor plans to continue with shoulder improvements this summer in the section between N. Shallowford and Dunwoody Park.
Some materials for projects like this are becoming more difficult to secure. Fortunately, we've had a recent delivery of stormwater pipe to keep the project moving. The project is scheduled to be completed in 2024.
Click here to subscribe to future updates.
|