Construction Progress Crew are hard at work finalizing the exterior of the main building. Sidewalks and patios are scheduled to be poured along with the installation of exterior lighting. In the Independent Living building, crews are focusing on the cabinets, counter tops and flooring, and painting continues in the common spaces. Hard tile flooring and equipment installation is progressing in the kitchen/dining area, and plumbing, electrical and HVAC contractors are finalizing “rough-in” systems on all floors in the Assisted Living building. The Memory Care building is now enclosed and watertight with HVAC duct work underway. Painting is complete and hard flooring installation continues in two of the Casettas. In the third Casetta, the framing and shingle installation is complete, and the concrete slab is poured with wall framing ongoing in the fourth Casetta. |