Lift:
On Friday April 25th to Sunday April 27th a 500 Ton will be hoisting a chiller to the roof at 330 W. Grand Ave.that will require a full street closure. This will take place from 9:00 AM Friday to 8:00 PM Sunday. Bus Stop #65 Grand will be affected.
For questions, please contact John Mooncotch Jr. - Royal Crane - 708-774-2087
Casino Caisson Pours: March 18 - May 18
- Total duration of caissons and piles is approximately 8 weeks (approximately mid-May)
- Start date of caissons: Permits are expected to be issued by March 14
- Casino and Hotel caissons – A total of 356
- Casino Piles – A total of 202
Work hours will continue to be 8am-8pm. However, if an issue arises during a pour, there is the potential that crews will work past 8pm. Once a caisson pour begins, it can't stop until it is finished.
676 North Michigan Avenue Façade Project
Redmond Construction was hired to complete a façade project at 676 North Michigan Avenue. Currently, the following closures are in-place:
- Sidewalk on the south side of Huron, from Michigan Avenue to a point 150' west thereof
- Curb lane on the south side of Huron, from Michigan Avenue to a point 150' west there of is being used as a pedestrian walkway
- Partial sidewalk closure the west side of Michigan, from Huron to a point 100' south thereof
This project is expected to be completed by fall 2025.
River North Lighting Project
The Chicago Department of Transportation (CDOT) has completed new light pole installation in the area bounded by Chicago, Ontario, Orleans, and the River. CDOT has begun removal of the old light poles and continues to restore infrastructure trenching.
Pin & Link Project on Randolph and Columbus
CDOT crews are scheduled to perform steel work and bridge expansion joint rehab along Randolph Street, Columbus Drive, and Stetson Avenue. Please see details below:
General Construction Schedule:
7:00 am - 3:30 pm, Monday - Friday; with the occasional extension to 5:30 pm as needed.
Scope of Work and Access Impacts During Construction:
In general, one lane of travel will be open at all times along each roadway, level, and direction. Access along sidewalks will remain open with detours around the work areas.
This project is expected to be completed at the end of June 2025. Asphalt restoration will occur in July 2025.
Casino Demolition Update
The demolition team will begin site concrete crushing operations over the next eight weeks. The operation with run from 8 AM until 5 PM. The crusher will be placed in between the Ontario feeder ramp and the southern edge of the current building.
|