Work has happened concurrently on Pierce St. and Grant St., but they are different parts of the pipe replacement process. Check out the graphic in the next section to see the difference in phases of work.
Pierce St. and W. 22nd Ave.
Crews have replaced the larger water main down the length of the street. There may be a pause in the work as the next phase is scheduled. Once work resumes, you will see crews move down the street to connect the smaller service pipes that lead to individual homes and businesses. If crews need to shut your water off or block your driveway access to complete work, they will notify neighbors and provide additional information directly ahead of time.
Grant St. and W. 23rd Ave.
Crews are currently being scheduled to replace the water main. Expect construction activity to pick up on these streets once work begins.
|