Bridges and Tunnels:
Hampton Roads Bridge-Tunnel, I-64:
- Alternating, single-lane closures eastbound Sept. 28-Oct. 1 from 9 p.m. to 5 a.m.
- Full directional closures planned in October for tunnel repaving, with only one direction closed at a time. View the full traffic alert. The list of scheduled dates, alternate travel routes and updated information can be found at https://vdot.virginia.gov/hrbtclosures.
Hampton Roads Bridge-Tunnel (HRBT) Expansion Project:
- Single-lane closures on I-64 in both directions from Willoughby Bay Bridge to Patrol Road Sept. 27-Oct. 3 from as early as 8 p.m. to as late as 7 a.m.
- Single-lane closures on I-64 in both directions at the HRBT Sept. 28-Oct. 2 from as early as 9 p.m. to as late as 9 a.m.
- A series of intermittent stoppages on I-64 in both directions between Mallory Street (exit 268) and HRBT Sept. 28-Oct. 2 from 10 p.m. to 5 a.m.
- Full ramp closures from as early as 8 p.m. to 5 a.m.:
- I-64 west off-ramp to W. Bay Avenue (exit 274) Sept. 28-Oct. 4
- I-64 east off-ramp at Mallory Street (exit 268) Sept. 28, Oct. 1
- W. Bay Avenue on-ramp to I-64 east Sept. 28-Oct. 2
- I-64 east off-ramp to 4th View Street Sept. 28-Oct. 3
Monitor-Merrimac Memorial Bridge-Tunnel, I-664:
- Alternating, single-lane closures in both directions Sept. 28-Oct. 1 from 9 p.m. to 5 a.m.
James River Bridge, Route 17:
- Alternating, single-lane closures in both directions Sept. 28-30 from 9 a.m. to 2 p.m.
George P. Coleman Bridge, Route 17:
- Single-lane closures northbound Sept. 29 from 9 a.m. to 3 p.m.
- A series of test openings Sept. 29 between 7-8 p.m.
Elizabeth River Crossings (Downtown/Midtown Tunnels):
- Go to DriveERC.com for scheduled closures on the Downtown Tunnel (I-264), Midtown Tunnel (Route 58) and MLK Expressway (Route 164).
| |
I-64, Chesapeake:
- Full ramp closures from I-64 east to I-464 north (exit 291A):
- Sept. 27
- from 12:01 a.m. to 8 a.m.
- from 10 p.m. to 5 a.m.
- Sept. 28-Oct. 2 from 11 p.m. to as late as 6 a.m.
- Full ramp closures from I-64 east to I-464 south (exit 291B):
- Sept. 27
- from 12:01 a.m. to 8 a.m.
- from 10 p.m. to 5 a.m.
- Sept. 28-29 from 11 p.m. to 5 a.m.
| |
I-64 Gap Segment C Widening, James City County:
- Single-lane closures on I-64 in both directions from the New Kent County-James City County line to Route 199/Lightfoot (exit 234) Sept. 27-Oct. 2 from as early as 7 p.m. to as late as 6 a.m.
- Brief, intermittent stoppages on Six Mount Zion Road in both directions Sept. 28-Oct. 2 from 9 a.m. to 3 p.m.
| |
I-64, Hampton Roads Express Lanes (HREL):
|
I-64, Norfolk Reversible Express Lanes:
- Full closure in both directions:
- Continuously from 8 p.m. Sept. 25 until 3 a.m. Sept. 28
- Sept. 27-Oct. 1 from 8 p.m. to 3 a.m.
- Sept. 28-Oct. 2 from 9:30 am. to 12:30 p.m.
- Continuously from 8 p.m. Oct. 2 until 3 a.m. Oct. 5
|
I-64, Chesapeake Express Lanes:
- Full Express Lanes closures westbound between the High Rise Bridge and Greenbrier Parkway (exit 289) Sept. 27-Oct. 3 from as early as 8 p.m. to as late as 10 a.m.
- Alternating, mobile Express Lanes closures in both directions between I-264 (exit 284) and Indian River Road (exit 286) Sept. 27-29 from 9 p.m. to 5 a.m.
- Alternating, mobile Express Lanes closures eastbound between Greenbrier Parkway (exit 289) and the High Rise Bridge Sept. 27-29 from 9 p.m. to 5 a.m.
- Full Express Lanes closures eastbound between Indian River Road (exit 286) and the High Rise Bridge Sept. 29 from 11 p.m. to 3 a.m.
|
I-64, HREL Hampton 4C Project:
- Full ramp closures on I-64 Sept. 27-Oct. 3 from as early as 9 p.m. to 5 a.m. (Non-conflicting ramp closures may be in place concurrently):
- Off-ramp from I-64 west to Armistead Avenue/LaSalle Avenue (exit 265B)
- Off-ramp from I-64 east to Rip Rap Road, Armistead Avenue/Langley AFB (exit 265C)
- On-ramp from Settlers Landing Road/Woodland Road to I-64 west
- Off-ramp from I-64 east to Settlers Landing Road/Woodland Road (exit 267)
- On-ramp from Settlers Landing Road/Woodland Road to I-64 east
- Off ramp from I-64 west to Settlers Landing Road/Woodland Road (exit 267)
- Alternating, single-lane closures on I-64 in both directions from Mallory Street (exit 268) to LaSalle Avenue (exit 265) Sept. 27-Oct. 3 from 10 p.m. to 5 a.m.
- Brief, intermittent stoppages on I-64 in both directions between Mallory Street (exit 268) and LaSalle Avenue (exit 265) Sept. 28-Oct. 4 between 12:01 a.m. and 4 a.m.
- Full closure of I-64 east between Rip Rap Road (exit 265C) and Settlers Landing/Woodland Road (exit 267) Sept. 30 (backup dates Oct. 1-2) between 12:01 a.m. and 4 a.m., with signed detours in place.
- Long-term, continuous single-lane closure on I-64 in both directions, reducing travel lanes from three to two lanes between Settlers Landing Road/Woodland Road (exit 267) and LaSalle Avenue (exit 265A).
|
I-64, HREL Norfolk 1A Project:
- Alternating single-lane closures on I-564 from I-64 to Terminal Boulevard:
- Eastbound Sept. 27-Oct. 2 from as early as 7 p.m. to 3 p.m.
- Westbound Sept. 27-Oct. 2 from as early as 9 a.m. to 4 a.m.
- Brief, intermittent stoppages along I-64 east between Granby Street (exit 276) to Chesapeake Boulevard (exit 279) Sept. 27-Oct. 2 from as early as 10 p.m. to 5 a.m.
- Full ramp closures from I-564 east to I-64 west Sept. 27-Oct. 2 from 8 p.m. to 5 a.m.
- Full off-ramp closures from I-564 east to I-64 east Sept. 27-Oct. 2 from 7 p.m. to 5 a.m.
- Full off-ramp closures from I-64 west to I-564 west Sept. 27-Oct. 2 from 10 p.m. to 4 a.m.
- Full off-ramp closures from I-64 west to Granby Street (exit 276A) Sept. 27-Oct. 2 from as early as 8 p.m. to as late as 7 a.m.
- Full off-ramp closures from I-64 east to Granby Street/I-564 west (exit 276A) Sept. 27-Oct. 2 from as early as 9 p.m. to as late as 7 a.m.
- Full on-ramp closures from Patrol Road to I-64 east Sept. 27-Oct. 2 from as early as 9 p.m. to as late as 7 a.m.
- Full off-ramp closures from I-64 west to Tidewater Drive (exits 277A and 277B) Sept. 27-Oct. 3 from as early as 10 p.m. to 5 a.m.
- Full off-ramp closures from I-64 east to Tidewater Drive (exits 277A and 277B) Sept. 27-Oct. 2 from as early as 10 p.m. to as late as 7 a.m.
- Full on-ramp closures on Tidewater Drive in both directions to I-64 west Sept. 27-Oct. 2 from as early as 8 p.m. to as late as 7 a.m.
- Full on-ramp closures on Tidewater Drive to I-64 east Sept. 27-Oct. 2 from as early as 10 p.m. to as late as 7 a.m.
- Full off-ramp closures from I-64 west to Little Creek Road (exit 276C) Sept. 27-Oct. 3 from as early as 10 p.m. to 5 a.m.
- Full off-ramp closures from I-564 east to Little Creek Road (exit 4) Sept. 27-Oct. 2 from 7 p.m. to 5 a.m.
- Full on-ramp closures from Little Creek Road to I-64 east Sept. 27-Oct. 2 from as early as 10 p.m. to as late as 7 a.m.
- Single-lane closures on I-64 east on the Willoughby Bay bridge from 15th View Street (exit 272) to 4th View Street (exit 273) Sept. 28-Oct. 1 from as early as 9 p.m. to 5 a.m.
- Alternating single-lane closures on I-64 in both directions from Granby Street (exit 276) to Chesapeake Boulevard (exit 278) Sept. 28-Oct. 1 from as early as 7 p.m. to 5 a.m.
- Alternating single-lane closures on I-64 in both directions from Granby Street (exit 276) to Chesapeake Boulevard (exit 278) continuously from as early as 7 p.m. Oct. 2 to 5 a.m. Oct. 5. (No eastbound work on Oct. 4 between 11 a.m. and 3 p.m.)
- Long-term single-lane closure on southbound Tidewater Drive at the I-64 overpass reopened on Sept. 21. View the full traffic alert.
- Long-term full on-ramp closure from southbound Tidewater Drive to I-64 east with new left turn at Thole Street to access I-64 east.
|
I-64, HREL Newport News/Hampton 4A/4B Project:
- Single-lane closures on I-64 in both directions from I-664 to Rip Rap Road Sept. 27-Oct. 3 from as early as 11 p.m. to as late as 5 a.m.
- Single-lane closures on I-64 in both directions from Denbigh Boulevard to Mercury Boulevard (exit 263) Sept. 27-Oct. 4 from as early as 8 p.m. to as late as 5 a.m.
- Full closure of the ramp from I-664 north to I-64 east Sept. 27-Oct. 4 from as early as 10 p.m. to as late as 5 a.m.
- Full closure of the ramp from Armistead Avenue to I-64 west Sept. 27-Oct. 4 from as early as 10 p.m. to as late as 5 a.m.
- Full closure of the I-64 west ramp to I-664 south (exit 264A) Sept. 27-Oct. 4 from as early as 10 p.m. to as late as 5 a.m.
- Full closure of the I-64 west off-ramp to southbound LaSalle Avenue (exit 265A) Sept. 27-Oct. 4 from as early as 10 p.m. to as late as 5 a.m.
- Long-term single-lane closure on I-64 east near Victory Boulevard (exit 256) through early fall 2026. View the full traffic alert.
- Long-term outside single-lane closures in both directions on LaSalle Avenue from North Armistead Avenue to Michigan Drive. View the full traffic alert.
- Long-term, full on-ramp closure from Lasalle Avenue to I-64 east. View the full traffic alert.
-
Long-term, traffic shifts and lane reductions from three to two lanes on I-64 in both directions from the I-664 interchange to Armistead Avenue. View the full traffic alert.
- Traffic shift and long-term single-lane closure of the outside right lane on I-64 west near Hampton Roads Center Parkway. View the full traffic alert.
|
I-464, Chesapeake:
- Full ramp closures from I-464 south to I-64 east (exit 1B) Sept. 27 from 8 p.m. to 5 a.m.
- Full on-ramp closures from Route 17 (Dominion Boulevard) north to I-464 north (exit 17B):
- Continuously from 5 a.m. Sept. 27 to 5 a.m. Sept. 28
- Sept. 28-Oct. 3 from 9:30 a.m. to 3 p.m.
- Sept. 28-Oct. 2 from 8 p.m. to 5 a.m.
- Continuously from 5 a.m. Oct. 3 to 5 a.m. Oct. 4
| |
Intermodal Connector, Norfolk:
- Full off-ramp closures of the Intermodal Connector west ramp to Seabee Road Sept. 28-Oct. 2 from 9:30 a.m. to 4:30 p.m.
| | | | |