NOVEMBER 2026 

KE KULEANA O KE ALAKAU PAUKIKĪ O HONOLULU

Project Update - Monthly Newsletter. HART Logo on the right.

IWILEI DRONE VIDEO UPDATE

Iwilei Drone Video Cover

Drone footage of Iwilei Station and area

This aerial drone video offers a bird’s-eye view of the Iwilei area and the site of the future Kūwili (Iwilei) Skyline Station. 


Located near the intersection of Dillingham Boulevard and Kaʻaahi Street, the Iwilei Station will be at the center of the City’s Transit-Oriented Development plan and will provide direct access to a revitalized community with newly developed housing, jobs, shops, services, and public spaces.


> View Video

KAKAʻAKO CONSTRUCTION BEGINS

Halekauwila Street Lane Closure Map

Initial traffic plan on Halekauwila Street

Guideway construction has commenced on Halekauwila Street, beginning with the first section between Richards and Punchbowl Street, as Skyline continues to progress through Downtown Honolulu and toward the Civic Center Station in Kakaʻako. 


New traffic plans will be installed as work progresses. Residents, businesses and motorists will experience traffic changes, detours, and other construction-related impacts during this time.


> View Construction Notice


APTA INNOVATION AWARD

HART, DTS and Hitachi staffs at APTA Award ceremony

Award ceremony at APTA Expo in Chicago, IL 
(Courtesy of Hitachi Rail Honolulu)

HART, DTS and Hitachi staffs at APTA Award ceremony

APTA Expo in Chicago, IL 
(Courtesy of Hitachi Rail Honolulu)

The City and County of Honolulu received the prestigious American Public Transportation Association (APTA) Innovation Award, which honors transit agencies and organizations that demonstrate groundbreaking concepts or problem-solving techniques in mobility. 


Skyline is the first fully automated light metro system in the United States and the nation’s first transit system with automated platform screen gate technology. Skyline utilizes an Automated Train Control system that serves as the intelligent center, enabling fully automated train operation. 


Other key automated functions include automated yard operations to dispatch and stable trains, automated train parking function, automated tracking, monitoring and analysis of maintenance activities, automated coupling of trains for rescue operations, automated diagnostics to find and locate system failures, automated staggering of train starts at stations to reduce peak power demand, automated system service performance monitoring and reporting, and advanced analytics integrated into Skyline’s closed-circuit television (CCTV) system. 


> View photos

 

SEGMENT 3 CONSTRUCTION UPDATES

 
Construction Progress Infographic - City Center Guideway and Station

Skyline Segment 3 Construction Progress

Shafts (foundations): 38/148 complete

Columns (piers): 23/148 complete

Caps: 6/148 complete

October 30, 2026


> View infographic

Utility Relocations Infographic - Construction Status

Utility Relocation Progress

Dry Utilities: 97% complete

Wet Utilities: 97% complete

Electric Utilities: 74% complete

October 30, 2026


> View infographic

 

PROJECT STATUS

Rail Construction Progress 71.3%

STAY CONNECTED

Icon - Work Suitcase

WORK WITH US

Icon - Board meeting people

BOARD OF DIRECTORS

Icon - Shop Open Sign

SHOP & DINE ON THE LINE

Icon - Event Calendar

EVENT CALENDAR

 
 

FOLLOW US

Facebook  Instagram  X  YouTube  LinkedIn
 
Footer -  Orange Wave graphic