Meet the construction contractor and learn about upcoming traffic impacts for the Walker Road and Murray Boulevard Intersection Project.
In-Person Open House
Tuesday, March 24 from 5–7 p.m.
B4 Church, 13565 SW Walker Road
Construction is expected to begin this summer and continue through 2028.
The project will improve the intersection with dual left‑turn lanes, dedicated right‑turn lanes, and a new southbound lane on Murray Boulevard.
Work also includes replacing two bridges over Cedar Mill Creek and multiple culverts on Walker Road. A closure of Walker Road east of Murray Boulevard is expected in summer 2027 for culvert replacement.
This project is being delivered in partnership with the City of Beaverton, Clean Water Services, and Tualatin Valley Water District.
|