Jackson Creek Parkway (JCP) Project

Construction Update

June 23, 2023


 Monument Junction Interim Improvements

 

The Monument Junction project contractor, Wildcat Construction, continues its widening efforts along Jackson Creek Parkway’s northbound roadside.


Wildcat is working on the east side of the northbound lane in preparation for Martin Marietta to place base course material on the roadway.


Martin Marietta is scheduled to mobilize Tuesday (06/27) to begin placement of the base course to the roadway starting on the south end of the project and working to the north end of the project. This operation is expected to last approximately one week, weather dependent.


Following the placement of the base course material, Martin Marietta will begin paving operations for Phase 1 (east side, northbound lane) of the project. This work, barring any weather complications, is also expected to last approximately a week.



Along with the roadway preparation, Wildcat has been performing Utility Potholing investigations for visual confirmation of each underground utility type, size, depth, and orientation.



This “Interim” project will see approximately 2,600 linear feet of Jackson Creek Parkway street improvements including widening for several new turn lanes, drive access to development areas, signage, and striping.

 

The project is scheduled for completion in August 2023.


For the safety of the traveling public and construction crews, please adhere to the reduced speed limit along the north end of Jackson Creek Parkway and be cautious of trucks and construction vehicles operating in the area.

CLICK TO BE ABLE TO ENLARGE THE MAP

OVERVIEW AND TIMELINE OF PROJECTS


Monument Junction Interim Improvements (Project A) – Classic Homes (Construction duration: three months during summer 2023)

This “Interim” project by Classic Homes will see approximately 2,600 linear feet of northern JCP street improvements including widening for several new turn lanes, drive access to development areas, signage, and striping. 


The “Ultimate Improvements” (Project D) to this northern section of Jackson Creek Parkway will take place during the Town of Monument’s Jackson Creek Parkway Widening Project estimated to start construction in late 2024.

Highway 105A Construction (Project B) – El Paso County (Construction duration: summer 2023 – 2025)

This project extends the 4-lane section of Highway 105 from just east of the intersection of Jackson Creek Parkway to Lake Woodmoor Drive. It includes widening and reconstruction of Highway 105, new curb and gutter, two retaining walls, intersection improvements, new roundabout at Knollwood Drive/Village Ridge Point intersection, traffic signal replaced at Knollwood Drive, a new underground storm drainage system and water quality pond. 

  • Monument Academy will construct new queuing lanes on the school property site north of Highway 105.
  • The Monument Junction developer will construct improvements at the Highway 105/CO-105/Jackson Creek Parkway (JCP) intersection including a second westbound left turn lane on Highway 105 to southbound Jackson Creek Parkway.


Jackson Creek Parkway Widening (Project E) – Town of Monument (Construction duration, expected late 2024 - 2026)

This project will expand Jackson Creek Parkway from one lane in each direction to two lanes in each direction (from Higby Road north to Highway 105), extending the four-lane configuration. Also included are drainage improvements, median landscaping, pedestrian and bike pathways, and “Gateway” treatments.

Stay Informed on the Highway105A/CO-105/Jackson Creek Parkway (JCP) Projects 

Recorded Message Phone: 719-423-8100

Sign up for project updates by sending an email to: 

Hwy105Aconstruction@gmail.com

JacksonCreekPkwy@gmail.com

 

Project Websites:  

Hwy 105a: Link to El Paso County project website     

https://www.jacksoncreekpkwy.com/