Highway 105 Project Nears Major Milestone, Reopens Prior to Holidays
You may have seen that the Highway 105 project construction team has removed significant traffic control devices to allow for the opening of Highway 105 in advance of the holiday season. The speed limit on Highway 105 through the project has also been be increased from 20 MPH to 30 MPH. While major construction activities as well as asphalt and striping work are completed, there are still several tasks that remain.
For the next few weeks, traffic will continue to be shifted to travel in the inner lanes as the team concentrates on final shoulder grading, finishing the sidewalks, and landscaping work. The daily lane closures will be reopened each evening.
With many of the traffic control devices removed, there will be a tendency to drive faster. Please adhere to the speed limit of 30MPH as the area is still an active construction zone with crews at work. Please continue to exercise caution while driving through the project area for your safety and for that of the construction crews who are still actively working in the outer lanes.
We are continually monitoring traffic control and making changes as needed to minimize impacts as much as possible.
|