Highway 105A Construction UPDATE

January 30, 2024

Upcoming Construction Work


Additional traffic shifts due to utility work along Highway 105 is anticipated to begin Feb 2 and continue through the weekend. The majority of this work is anticipated to be completed by the following Monday morning prior to rush hour.


A waterline line install is scheduled to begin the week of Feb 5 and planned to be completed in about two weeks. During the second week of work, the northbound Knollwood traffic approaching Hwy 105 will be reduced to a single lane. All vehicles making left turns, proceeding straight north, and making right turns will use the “Right Turn Lane”. 


Anticipated schedule is weather and resource dependant and subject to change.

Friendly Reminder


Throughout the workday, there are various project requirements that require traffic shifts and the closure of additional lanes. It is expected that certain activities on this project will demand extra lane closures and the presence of flaggers, among other measures. The modification of traffic lane usage is crucial for ensuring the safety of the workers and the traveling public. Although it may cause inconvenience at times, prioritizing safety is of utmost importance. We greatly appreciate your ongoing patience and understanding for the duration of the project.

Click here for tips on how to navigate a roundabout

Click here to view a video on how to navigate a roundabout

Alternate routes suggested during Monument Academy student drop off/pick up times


We understand that Monument Academy student drop-off and pick-up times can cause traffic delays. To ensure a smoother experience for non-school traffic, we recommend finding an alternate route, if possible, that avoids this particular area during these times:

Mondays – Thursdays: 7 – 8:30 a.m. and 2:45 – 4 p.m.

Fridays: 7 – 8:30 a.m. and 11:30 a.m. – 1 p.m.

The estimated schedule is based on the best information available at this time and is weather and resource-dependent.


We are continually monitoring traffic control and making changes as needed to minimize impacts as much as possible.


Construction of Hwy. 105 improvements will continue early into 2025.

MULTIPLE ROADWAY AND UTILITY PROJECTS


There are multiple roadway and utility projects both underway and planned for this area of the community being led by different jurisdictions. The project teams are coordinating efforts to minimize impacts to the traveling public as much as is possible. ALTERNATE ROUTES, IF POSSIBLE, ARE HIGHLY ADVISED.

Highway 105A Construction (Project B) – El Paso County (Construction duration: July 24, 2023 – expected to continue into 2025)

The project extends the 4-lane section of Highway 105 just east of Jackson Creek Parkway to Lake Woodmoor Drive, providing for greater mobility by accommodating more traffic. The new configuration will be two lanes in each direction with left and right turn lanes. The project also includes multi-use shoulders and pedestrian improvements, sidewalk connectivity, replacement of the traffic signal at Knollwood Boulevard, a new underground drainage system, and water quality pond, and a new roundabout at the Knollwood/Village Ridge Point intersection. The new roundabout coupled with new queuing lanes being constructed by Monument Academy are designed to keep traffic moving and reduce the traffic backups on Highway 105 that have previously occurred in this area.

CLICK TO VIEW MAP  

Hwy105A Construction and Monument Junction Interim JCP Improvements

Stay Informed

Recorded Message Phone: 719-423-8100

Sign up for project updates by sending an email to: 

Hwy105Aconstruction@gmail.com

JacksonCreekPkwy@gmail.com

 

Prior versions of the newsletters and project maps are available on the project websites:  

Hwy 105a: http://EPC-Hwy105AConstruction.com/

Jackson Creek Parkway: https://www.jacksoncreekpkwy.com/