Upcoming Traffic Shift to North Side of Highway 105
Starting late July or early August, the project will transition to a new phase of work on the south side of Highway 105. Traffic traveling in both directions will be shifted to the north side of Highway 105 for the remainder of the project until the planned opening in late 2024. Intermittent lane closures and flagging operations should be expected.
The estimated schedule is based on the best information available at this time and is weather and resource-dependent.
We are continually monitoring traffic control and making changes as needed to minimize impacts as much as possible.
Construction of Highway 105 improvements will continue into spring 2025.
|