Northbound Knollwood Closure


Knollwood, north of Highway 105, will be closed on Saturday, October 26th, to allow for the final striping of the roadway. The road will be closed north of the roundabout and Highway 105, there will be no through access to Village Ridge Point. The road will reopen once the striping has been properly set. Alternative routes are highly advised during this closure.

We are continually monitoring traffic control and making changes as needed to minimize impacts as much as possible.


Flagger operations should be expected throughout the remainder of the project.


Construction of Highway 105 improvements will continue into spring 2025.


The estimated schedule is based on the best information available at this time and is weather and resource-dependent.

Monument Academy Traffic


To ensure a smoother experience for non-school traffic, we recommend finding an

alternate route, if possible, that avoids this area during these school drop off/pick up times:

Mondays – Thursdays: 7 – 8:30 a.m. and 2:45 – 4 p.m.

Fridays: 7 – 8:30 a.m. and 11:30 a.m. – 1 p.m.

MULTIPLE ROADWAY AND UTILITY PROJECTS


There are multiple roadway and utility projects both underway and planned for this area of the community being led by different jurisdictions. The project teams are coordinating efforts to minimize impacts to the traveling public as much as possible. ALTERNATE ROUTES, IF POSSIBLE, ARE HIGHLY ADVISED.

Highway 105A Construction – El Paso County (Construction duration: July 24, 2023 – expected to continue into spring 2025)

The project extends the 4-lane section of Highway 105 just east of Jackson Creek Parkway to Lake Woodmoor Drive, providing greater mobility by accommodating more traffic. The new configuration will be two lanes in each direction with left and right turn lanes. The project also includes multi-use shoulders and pedestrian improvements, sidewalk connectivity, replacement of the traffic signal at Knollwood Boulevard, a new underground drainage system and water quality pond, and a new roundabout at the Knollwood/Village Ridge Point intersection. The new roundabout, coupled with new queuing lanes constructed by Monument Academy, are designed to keep traffic moving and reduce the traffic backups on Highway 105 that have previously occurred in this area.

CLICK TO VIEW MAP  

Hwy105A Construction and Monument Junction Interim JCP Improvements

Stay Informed

Recorded Message Phone: 719-423-8100

Sign up for project updates by sending an email to: 

Hwy105Aconstruction@gmail.com

JacksonCreekPkwy@gmail.com

 

Prior versions of the newsletters and project maps are available on the project websites:  

Hwy 105a: http://EPC-Hwy105AConstruction.com/

Jackson Creek Parkway: https://www.jacksoncreekpkwy.com/