DATE: Friday, 7/30/21
TRAFFIC IMPACT:
The traveling public should expect intermittent periods of alternating one-way traffic within the project area between 9:00 a.m. and 3:00 p.m. Monday through Friday next week (8/2-8/6). Minor delays may occur.
CONSTRUCTION ACTIVITIES:
Permanent line striping has been completed.
Painting of roadway symbols and some sign installation remains. The contractor will be onsite completing this work at various times throughout the week next week.
Flagged traffic between the hours of 9:00 a.m. and 3:00 p.m. may occur when the contractor is onsite finishing remaining construction activities.