DATE: Thursday, 6/17/21
TRAFFIC IMPACT:
The traveling public should expect alternating one-way traffic within the project area between 9:00 a.m. and 3:00 p.m. Monday through Friday next week (6/21-6/25). Please expect delays and add extra time to your travel plans.
CONSTRUCTION ACTIVITIES:
Crews will have completed the necessary channel work along the Northeast side of Route 116 by the end of this week.
Throughout the week next week, the contractor will be engaged in spreading topsoil, seeding, mulching and restoring disturbed areas, and cleaning up the side of the road.
Expect flagged traffic from 9:00 a.m. to 3:00 p.m. throughout the week next week.