Hope South Campus Worship Center Project July 15, 2025 Update:

What's New with the Hope South Campus Building Project?

Our design team, Judd Dickerson Architects, BBM Structural Consultants, and Miller Professional Engineering (responsible for mechanical, electrical, and plumbing) have finalized the updated construction documents (drawings and specifications) for the redesigned Worship Center and have submitted them to Mark Cook Builders, our Contractor/Construction Manager for the Hope South Campus Building Project.  


Revised drawings prepared by CFB, which address site development, along with landscaping and irrigation plans from Michael Pape and Associates, are expected to be finalized by the end of July. Once completed, these documents will also be distributed to Mark Cook Builders and contract bidders.


While our design team was revising the drawings and specifications, Mark Cook Builders was simultaneously conducting the Prequalification and Evaluation Phase:


  • Develop prequalification criteria for evaluating subcontractors, including factors such as relevant experience, financial stability, safety record, appropriate licensing, bonding capacity, operational capabilities, and technical skills.
  • Develop a list of qualified subcontractors based on market expertise, proven performance, and alignment with the project's specific requirements and objectives, while also confirming their availability and interest.
  • Assess market trends, tariff effects, and material availability for key trades.
  • Suggest Value Engineering (VE) options by identifying alternative materials, systems, or methods that enhance value while maintaining quality and performance.


Mark Cook Builders is currently engaged in the Bid Solicitation and Review Phase:


  • Request bids from subcontractors who were prequalified in the Prequalification and Evaluation Phase.
  • Furnish pre-qualified subcontractors with the necessary construction documents, approved permits, drawings, and specifications.
  • Manage bidding among pre-qualified subcontractors by setting and enforcing deadlines.
  • Address any deficiencies or discrepancies identified in the construction documents with the architect to ensure timely resolution. Communicate all amendments promptly.
  • Review and address any discrepancies or redundancies within subcontractor scopes to guarantee comprehensive project coverage.
  • Conduct a thorough analysis of submitted bids to ensure completeness, alignment with project scope, schedule compatibility, and appropriate pricing. Present findings and recommendations to Hope Lutheran Church (HLC) building team regarding the selection of subcontractors for potential contract awards.


The Bid Solicitation and Review Phase is expected to conclude by the end of August 2025. Upon completion, Mark Cook Builders will submit the Guaranteed Maximum Price (GMP) to the Hope Lutheran Church (HLC) building team for review. The building team will then evaluate whether the proposed GMP meets the church's budgetary criteria and subsequently provide a formal recommendation to the Council and Congregation for approval.