Crews have completed CIDH (Cast-In-Drilled-Hole) pile installation for the new Cedar Avenue bridge over the railroad and are now beginning construction of the bridge abutments, which will support each end of the new bridge.
Work is currently underway at the first of two bridge abutments and is expected to continue for approximately three weeks. Crews will build the concrete support structure at the end of the bridge, including installing reinforcing steel, placing concrete, allowing the concrete to cure, and backfilling the area. Crews will also construct an exterior wall, which helps hold the surrounding soil in place and supports the transition between the bridge and the roadway.
During this phase of construction, residents and commuters may notice construction equipment, additional construction trucks traveling through the area, and construction noise near the work zone. Work schedules may change based on field conditions.
|