CONSTRUCTION UPDATE 

Week of September 13, 2026

PROJECT CLOSURES

There are no closures scheduled the week of September 13. All work will take place in protected work zones behind concrete barriers, also known as k-rail. At times, this work may be loud or cause dust and vibration. Traffic delays are expected. Motorists are encouraged to plan ahead, allow extra time to reach your destination or use alternate routes if possible.


Construction work will generally take place Monday through Friday during daytime hours (6:30 a.m. to 3:00 p.m.) and Sunday through Thursday during nighttime hours (8:00 p.m. to 5:00 a.m.).

BRIDGE FOUNDATION WORK

Crews have completed CIDH (Cast-In-Drilled-Hole) pile installation for the new Cedar Avenue bridge over the railroad. Work is now underway at both bridge abutments, which will support each end of the new bridge.


Through the end of September, crews will construct the concrete support structures at each end of the bridge by installing reinforcing steel, placing and curing concrete, and backfilling the areas. Crews will also construct exterior walls, which will help hold the surrounding soil in place and support the transition between the bridge and the roadway.


During this phase of construction, residents and commuters may notice construction equipment, additional construction trucks traveling through the area, and construction noise near the work zone. Work schedules may change based on field conditions.

CIDH piles at Abutment 2 for the new Cedar Avenue bridge over the Union Pacific Railroad.

All construction is dynamic and the schedule is weather-permitting and subject to change. Visit the Google map (project Google map) for the most up-to-date closures scheduled and available detour routes.


Si prefiere recibir información de construcción en español, llame al (877) 55-SBCTA.

CEDAR AVENUE BRIDGE RECONSTRUCTION

The Cedar Avenue Bridge over the I-10 and the railroad tracks will be widened in two stages.


The first stage, crews will complete the east side of the bridge over the I-10 freeway. During this time, traffic will be shifted to the opposite side (east half) of the bridge to allow crews to safely reconstruct the sidewalk and concrete barrier on the west half of the structure. To accommodate this shift, one lane will remain reduced in each direction on Cedar Avenue between Orange Street and Valley Boulevard.


Traffic delays should be expected during bridge reconstruction, please allow extra time to reach your destination and use caution when traveling through work zones. Alternate routes will include Slover Avenue or Valley Boulevard to Riverside Avenue to the east and Sierra Avenue to the west.


Following the reconstruction of the east side of the bridge, traffic will shift to the newly constructed portion of the bridge to allow for reconstruction of the west side of the bridge.


TEXT ALERTS

Receive our construction alerts on your mobile device. Sign up for text messages by texting i10Cedar to (888) 525-1021 (Reply STOP to cancel, text HELP for help. Normal text and data message rates apply).

ABOUT THE PROJECT

The I-10/Cedar Avenue Interchange Project is designed to relieve congestion, enhance safety, and improve traffic operations along Cedar Avenue between Bloomington Avenue and Orange Street. The project will widen the I-10 overcrossing and replace the railroad bridge, provide for roadway improvements along Cedar Avenue, and add capacity to the on- and off-ramps from Cedar Avenue to the I-10. During construction activities may include removing and rebuilding of existing and new structures, digging up roads for utility work, pavement and restriping work, installation of new traffic signals, traffic shifts, intermittent lane closures, and ramp closures. Workers and heavy equipment will be present throughout the project corridor and we ask that you allow for extra time to reach your destination as you may experience delays.

 