Crews continue to grade the eastbound and westbound I-10 shoulder between Live Oak Canyon Road and County Line Road as well as perform drainage work in the center median, behind concrete barriers, also known as k-rail. Construction activities are ongoing weekdays, Monday through Friday from 7:00 a.m. to 7:00 p.m.
In addition, crews are planning to complete nighttime drainage work from 10:00 p.m. to 6:00 a.m., Tuesday, June 17 and Wednesday, June 18 (into Thursday morning).
WHAT TO EXPECT: You may hear noise or feel vibration related to construction activity. Large vehicles are needed on-site to facilitate work and may be seen traveling in and out of the construction area. We encourage motorists to help take part in keeping everyone safe by obeying all construction signs.
|