Crews have begun constructing the bridge columns that will span across the new City Park Lake Bridge. This work began in late September and is anticipated to be completed late fall 2024. Once these have been installed, crews will begin working on the bridge arches, followed by setting girders in late 2024/ early 2025, weather permitting. These operations remain ongoing from Monday through Saturday during daytime hours.
Progress continues on the abutment and wing walls located along I-10 westbound by Dalrymple Dr. and E. Lakeshore Dr. The wall and wing wall forms have been installed for the walls on Dalrymple Dr. and crews will begin pouring concrete mid-October. Additionally, barrier and sound wall concrete operations have begun for the portion of I-10 westbound behind the Baywood Ave. area.
While work is ongoing, residents and motorists throughout the corridor can expect to see an increase in truck traffic, as well as an increase in noise during the day. Construction activities continue to be monitored by various noise and vibration monitors throughout the corridor.
|