Segment I Work Activities
Recently Completed
- Relocation of DMS signs to new overhead structures.
- Paved base for eastbound median.
- Completed concrete placements for Industrial Park Bridge deck.
Current Status:
- Sound Barrier Wall work including construction of foundation and footings, installing drainage.
- Pavement construction at bridge approaches (Fort Eustis Blvd. and Industrial Park Drive).
Upcoming Work Activities
- Continued sight distance clearing at Fort Eustis Boulevard ramps.
- Relocation of ITS systems.The ITS systems are the buried electric and communications cables usually associated with traffic cameras.
- Continue asphalt paving.
- Traffic shifts left into new median travel lanes.
Segment II Work Activities
Recently Completed
- Completed installation of temporary concrete barriers.
- Completed installation of Contrast Pavement Markings.
- Completed survey work for installation of MOT (Maintenance of Traffic) items.
- Layout of safety fence
- Removal of concrete curb island at Yorktown underpass.
Current Status:
- Continued clearing and grubbing operations throughout Segment II including the median in both east and west directions.
- Start installation of lane shifts and temporary pavement markings at bridge underpass locations on Jefferson Avenue, Yorktown Road, and Penniman Road.
- Continued installation of construction signs at bridge underpass locations on Jefferson Avenue, Yorktown Road, and Penniman Road.
Upcoming Work Activities:
- Continuing installation of MOT including construction signs and temporary pavement markings on bridge under-pass locations on Jefferson Avenue, Yorktown Road, Penniman Road, and Burma Road.
- Start bridge widening work
- Start work on existing and new drainage culverts
- Continuing installation of MOT including construction signs and temporary pavement markings on bridge underpass locations on Jefferson Avenue, Yorktown Road, Penniman Road, and Burma Road.
|