I-64 Southside Widening and High Rise Bridge Expansion Project
Upcoming Lane Closures
• Alternating, single-lane closures on I-64 in both directions between I-664 north/Route 13/Route 58 (exit 299) and Shell Road (overpass):
  • Dec. 13-16 from 7 p.m. to 5 a.m.
  • Dec. 17 from 9 p.m. to 7 a.m.
  • Dec. 18 from 8 p.m. to 9 a.m.
  • Dec. 19 from 8 p.m. to 5 a.m. 
• Triple-lane closure on I-64 east from Greenbrier Parkway (exit 289) to I-464 (exit 291) on Dec. 13 from 7 p.m. to 5 a.m. 
• Double-lane closure on I-64 east from I-464 (exit 291) to Great Bridge Boulevard (exit 292) on Dec. 14-15 from 7 p.m. to 5 a.m. 
Continuous Detour on Yadkin Road at the I-64 Overpass on Friday, Dec. 17, 5 a.m. to 5 p.m.

Motorists should be prepared for a continuous detour of Yadkin Road on Friday, Dec. 17, from 5 a.m. to 5 p.m., with a contingency date of Saturday, Dec. 18. Yadkin Road will be fully closed at the I-64 overpass. Local traffic will permitted to access to businesses on Yadkin Road from George Washington Highway. 

Motorists should utilize Galberry Road, Military Highway and George Washington Highway to navigate around the road closure. Detour information will also be designated with signage along the roadway. 

All construction schedules are pending, due to weather or unforeseen circumstances. Changes to the schedule will be updated on the project website traffic alerts page.
For a full listing of project impacts, visit Traffic Alerts on 64highrise.org.