Believe it or not, demolition of the YMCA lobby is happening SOON!
As we plan to transition into the next phase of construction, East Coast Construction and Farrar & Associates, Inc., have started to prepare our temporary entrance and handicap accessible entrance/exit in the Wellness Center. The following items will impact our facility over the next few weeks:
-
The front desk will be moved to the Wellness Center where our current handicap accessible entrance is located. To make room for this temporary desk/lobby, all cardio equipment in this area will be moved to alternative spaces within the Wellness Center on Monday, August 9th.
- Equipment to be relocated will include recumbent bikes and ellipticals. All other equipment will remain in place.
- We will be adjusting the height of our TVs as needed for member enjoyment.
-
Members, staff, and program participants will continue to access the facility through the current front entrance until further notice.
-
On Friday, August 13th, our IT company will be conducting necessary electrical work to transfer our internet server out of the demolition area.
- This work will most likely cause interruptions to our internet and phone systems - we apologize for any inconvenience in advance.
-
If you have questions and/or require assistance, please contact the appropriate department director.
-
During the week of August 16th, our check-in/registration area will be moved from it's current location over to the Wellness Center.
-
On Monday, August 23rd, our current lobby and front entrance will be officially closed to begin demolition.
As a reminder, your YMCA will remain fully operational through every phase of construction!
|