IMPORTANT PAINTING SCHEDULE UPDATE

SATURDAY OCTOBER 20, 2018


TO: MAJESTIC OWNERS AND MANAGEMENT COMPANIES:

Several rental management companies have inquired about the posssiblity of re-opening recently painted breezeways on Sundays instead of Mondays. They manage rental units on multiple floors, and when a floor is closed for painting, the guest is sometimes relocated to a floor that has just been painted.

Most of the current rental guests of Majestic Beach Resort have to get up and go to work on Monday mornings, and if a comparable unit on another floor is available, asking them to relocate on Monday before going to work would place an additional burden on an already stressful situation.

We checked with Valcourt, and they have agreed to allow us to open recently painted breezeway floors on Sundays at 1:00 PM rather than the previously published Mondays at 9:00 AM.

Of course, the closures and opening dates are still weather dependant. So far, the weather has cooperated, Hurricane Michael notwithstanding.

Hopefully, the weather will continue to be in our favor. The Association will let you know if there are any changes to the schedule.


Here is the revised schedule. ONLY THE OPENING DATES HAVE BEEN CHANGED

TOWER I

FLOORS 18, 19, 20, 21, 22, 23 - Complete. No further closure anticipated.

FLOORS 12, 13, 14, 15, 16, 17 - Were prepped on Monday 10/15/18 and painted on Tuesday 10/16/18, will reopen Sunday 10/21/18 at 1:00 PM.

FLOORS 6, 7, 8, 9, 10, 11 - Will close at 9:00 AM on Monday 10/22/18, will reopen Sunday 10/28/2018 at 1:00 PM.

FLOORS 2, 3, 4, 5 - Will close at 9:00 AM on Monday 10/29/18 and will reopen on Sunday 11/4/18 at 1:00 PM.


TOWER II


FLOORS 18, 19, 20, 21, 22, 23 - Will close at 9:00 AM on Monday 11/5/18 and will reopen on Sunday 11/11/18 at 1:00 PM.

FLOORS 12, 13, 14, 15, 16, 17 - Will close at 9:00 AM on Monday 11/12/18 and will reopen on Sunday 11/18/18 at 1:00 PM.

FLOORS 6, 7, 8, 9, 10, 11 - Will close at 9:00 AM on Monday 11/19/18 and will reopen on Sunday 11/25/18 at 1:00 PM.

FLOORS 2, 3, 4, 5 Will close at 9:00 AM on Monday 11/26/18 and will reopen on Sunday 12/2/18 at 1:00 PM.




WARNING: DO NOT WALK BAREFOOTED ANY WHERE IN OR AROUND MAJESTIC BEACH RESORT, INCLUDING BREEZEWAYS, BALCONIES, LOBBIES, POOLS, POOL DECKS, BOARDWALKS, BEACH, PARKING AREAS, ETC. SHARP OBJECTS MAY BE LAYING ON THE SURFACE OR EMBEDDED IN THE SAND

A "BOIL WATER" NOTICE REMAINS IN EFFECT FOR PANAMA CITY BEACH. USE BOTTLED WATER FOR DRINKING, TOOTHBRUSHES, ETC. USE BAGGED ICE.

SIGNS HAVE BEEN POSTED AROUND THE RESORT NOTIFIYING RENTAL GUESTS TO EXPECT REQUESTS FROM ADJUSTERS, INSPECTORS, ETC. TO ENTER UNITS. ENTRIES INITIATED BY THE ASSOCIATION WILL BE ACCOMPANIED BY A SECURITY OFFICER. PLEASE BE ON THE LOOKOUT FOR SCAMMERS PRETENDING TO BE ADJUSTERS OR CONTRACTORS.


ANNUAL MEETING: THE ANNUAL MEETING IS STILL SCHEDULED FOR NOVEMBER 3RD AT 10:00 AM. BECAUSE WE ARE SPENDING SIGNIFICANT SUMS OF MONEY TO RESTORE THE RESORT TO ITS PRESTORM CONDITION AS QUICKLY AS POSSIBLE, THE FRIDAY EVENING DINNER WILL NOT BE HELD THIS YEAR AND THOSE FUNDS WILL INSTEAD BE APPLIED TOWARDS PURCHASE OF MATERIALS NEEDED FOR REPAIR. MANAGEMENT IS LOOKING INTO A SCALED DOWN SOCIAL EVENT WITH CASH BAR AND LIGHT APPETIZERS. MORE ON THIS LATER....

AT THE MOMENT, WE ARE UNABLE TO ESTIMATE THE TOTAL COST OF REPAIRS, BUT WILL REPORT THE COSTS TO THE OWNERS AS SOON AS PRACTICAL.


ANOTHER UPDATE WILL BE SENT AS SOON AS EVENTS WARRANT.

Jimmy Lewis
President
Majestic Beach Resort Owners Association, Inc.


11212 Front Beach Road
Panama City Beach, FL 32407