The final coat of paint is complete on the second floor of the two story classroom section of the building and is being applied to the first floor. Ceiling tile is being installed in the extended learning areas and the cafeteria. In the main entrance section, the carpet is complete in the administration area and overhead electric devices are being installed in the main corridor and library. The gymnasium floor is being installed. Pipe installation and equipment wiring is underway in the mechanical room. In the kitchen, the floor is being installed along with electrical devices. Glass caulking, water line testing, access point wiring, and sprinkler system wiring continue throughout the building.