Indian Creek Drive Flooding Mitigation Phase III
Project Advisory - April 27, 2022
What's Happening
The new street light system along Indian Creek Drive is in its final testing phase. The lights will remain on during daytime and nighttime hours for approximately one week.
 
The following activities are scheduled along Indian Creek Drive and side streets:
  • Placing final pavement markings along side streets between Indian Creek Drive and Collins Avenue
  • Installing the final sections of the guardrail
  • Finalizing work at the pump station
  • Completing final inspections and performing punch list items 

This schedule may change due to unforeseen conditions or weather

Project Overview and Benefits
This project delivers vital improvements to the Indian Creek Drive community by providing new sidewalks, a lighting system and a continuous delineated bicycle path. It will also address flooding within the neighborhood by installing a comprehensive stormwater drainage system, including a water treatment system and generator in case of a power outage. The road and sidewalk will be rebuilt at a higher elevation to mitigate sea-level rise.

Who to Contact
Dexter Peralta, Neighborhood Affairs Coordinator
786.265.7443
To learn more about the city’s innovative initiatives, visit www.MBRisingAbove.com.

To request this material in alternate format, sign language interpreter (five-day notice required), information on access for persons with disabilities, and/or any accommodation to review any document or participate in any city-sponsored proceedings, call 305.604.2489 and select 1 for English or 2 for Spanish, then option 6; TTY users may call via 711 (Florida Relay Service).