|
Progress continues with near completion of the retaining wall which will make way for the eastbound right-turn lane onto Highway105 from Jackson Creek Parkway. Additionally, new traffic signal work at the intersection is scheduled to begin early this month.
Wildcat continues to work hard toward completing the project by the end of this year.
Upcoming Construction
The following work will impact some current traffic patterns and will change how the site currently looks:
- Currently working on grading the east side of Jackson Creek Parkway in preparation for road base, curb and gutter installation
- Installing two “pork chop” islands at the Highway 105/Jackson Creek Parkway intersection
- Two-inch “Mill and Overlay” work along Highway 105 (I-25 off-ramp to the east side of the Jackson Creek Parkway intersection)
- Striping along Highway 105 once the mill and overlay work is completed
- Storm mainline pipe installation down Jackson Creek Parkway
- Roadway subgrade prep and road base installation along Jackson Creek Parkway
- Paving followed by striping Jackson Creek Parkway
Completed Work
- Retaining wall construction on the east side of Jackson Creek Parkway and Highway 105 nears completion
- Right turn lane from Highway 105 southbound onto Jackson Creek Parkway.
- Drainage improvements on Highway 105 and the I-25 off-ramp
-
Traffic signals at Fat Tire Drive (not in use until signals at Jackson Creek Parkway and Highway 105 are operational)
- Right turn lanes at Laughing Lab Way and Fat Tire Drive on Jackson Creek Parkway
- Storm sewer work on Highway 105 that runs south under the retaining wall.
- Major fiber duct lowering at the Lumen Central Office
- Black Hills Energy gas relocation
- Mountain View Electric line relocation
- Lumen fiber duct lowering
- Woodmoor sanitary sewer line relocation
- Signalization at Fat Tire Drive
- Traffic delineators installed on Highway 105 eastbound for the right turn southbound on Jackson Creek Parkway
Concrete barrier traffic control for this project is in place. Construction work will occur inside that barrier wall. There will be no access restrictions to businesses.
Watch for trucks entering/exiting the construction area and for reduced speeds during construction. Use caution in the construction zone.
|