Monument Junction Project D (Jackson Creek Parkway

between Highway 105 and just north of Slopeside Street)

Project Update

October 2025

Highway 105 & Jackson Creek Parkway Intersection Project Milestones 

Progress continues with near completion of the retaining wall which will make way for the eastbound right-turn lane onto Highway105 from Jackson Creek Parkway. Additionally, new traffic signal work at the intersection is scheduled to begin early this month.

Wildcat continues to work hard toward completing the project by the end of this year.

 

Upcoming Construction

The following work will impact some current traffic patterns and will change how the site currently looks:

 

  • Currently working on grading the east side of Jackson Creek Parkway in preparation for road base, curb and gutter installation
  • Installing two “pork chop” islands at the Highway 105/Jackson Creek Parkway intersection
  • Two-inch “Mill and Overlay” work along Highway 105 (I-25 off-ramp to the east side of the Jackson Creek Parkway intersection)
  • Striping along Highway 105 once the mill and overlay work is completed
  • Storm mainline pipe installation down Jackson Creek Parkway
  • Roadway subgrade prep and road base installation along Jackson Creek Parkway
  • Paving followed by striping Jackson Creek Parkway


Completed Work

  • Retaining wall construction on the east side of Jackson Creek Parkway and Highway 105 nears completion
  • Right turn lane from Highway 105 southbound onto Jackson Creek Parkway.
  • Drainage improvements on Highway 105 and the I-25 off-ramp
  • Traffic signals at Fat Tire Drive (not in use until signals at Jackson Creek Parkway and Highway 105 are operational)
  • Right turn lanes at Laughing Lab Way and Fat Tire Drive on Jackson Creek Parkway
  • Storm sewer work on Highway 105 that runs south under the retaining wall.
  • Major fiber duct lowering at the Lumen Central Office
  • Black Hills Energy gas relocation
  • Mountain View Electric line relocation
  • Lumen fiber duct lowering
  • Woodmoor sanitary sewer line relocation
  • Signalization at Fat Tire Drive
  • Traffic delineators installed on Highway 105 eastbound for the right turn southbound on Jackson Creek Parkway

 

Concrete barrier traffic control for this project is in place. Construction work will occur inside that barrier wall. There will be no access restrictions to businesses.

 

Watch for trucks entering/exiting the construction area and for reduced speeds during construction. Use caution in the construction zone.

Newly constructed retaining wall and grading along the east side of Jackson Creek Parkway in preparation for road base and curb and gutter installation, making way for the eastbound right-turn lane onto Highway 105. 

Project Description


Construction by the Monument Junction Metro District’s contractor, Wildcat, is underway to support the Monument Junction development. This is the ultimate build-out of the intersection at Jackson Creek Parkway and Highway 105. The Jackson Creek Parkway Interim work previously completed was tied directly to Monument Junction for access to both.

Stay Informed

For more information about the Jackson Creek Parkway Widening project, visit our website HERE


Send an email asking to receive project updates to: JacksonCreekParkway@gmail.com