Like us on Facebook  Follow us on Twitter



February 2016
Runway 13/31 Project
The runway reconstruction project is still in a holding pattern as we wait for the weather to reach consistently warm temperatures overnight.

We anticipate a coal tar seal to be applied in March. Following the 30 day cure time, final striping will be applied and the runway will be permanently opened.

You've probably noticed all the PAPIs have been installed but not turned on. We're in the queue for an FAA flight check. Once we get the thumbs up, they'll go live.

In the meantime, Runway 13/31 is open with the temporary striping shown in the picture below.

Please continue to check NOTAMs and don't hesitate to give us a call if you have any questions. We thank you for your continued patience.
g


It's Official

Our name change - to San Marcos Regional Airport - can be found in the FAA's latest Airport/Facility Directory!

The change will continue to trickle down to other publications as they are updated on their own schedules.
g
Security Fence
Construction on the fence that will separate vehicular traffic from the ramp started today!

The 4' high fence, which will look similar to the one pictured above (without the spikes) will serve to protect against incursions from visitors who do not require ramp access. A total of five (5) electric gates will allow tenants to access their aircraft. Pedestrians will be able to access the ramp via openings at various points in the fence.

Additionally, parking lots near the City-owned t-hangars and CAF will be constructed for added parking outside the fence.

We anticipate the project to be complete within three to four months.
g
Upcoming CAF Events

Fly-In/Drive-In
When: April 16   12:30-3:30pm
Cost: Free
See website for more information

Casino Night
When: April 23   6:00-10:00pm
Cost: $45.00
See website for tickets and information

g
Professionally managed by
HYI (512) 216-6039
TAP (512) 216-6042