Runway 13/31 Project
The runway reconstruction project is still in a holding pattern as we wait for the weather to reach consistently warm temperatures overnight.
We anticipate a coal tar seal to be applied in March. Following the 30 day cure time, final striping will be applied and the runway will be permanently opened.
You've probably noticed all the PAPIs have been installed but not turned on. We're in the queue for an FAA flight check. Once we get the thumbs up, they'll go live.
In the meantime, Runway 13/31 is open with the temporary striping shown in the picture below.
Please continue to check
NOTAMs and don't hesitate to give us a call if you have any questions. We thank you for your continued patience.
|