SHARE:  
Click the buttons below to open a section in a browser window or scroll down
Help us grow the Kiewit Innovation community by encouraging your colleagues to subscribe to our newsletter. If they use this link and provide your email address, you'll earn 2 points for each new subscriber. You can cash in points you earn for Kiewit Innovation loot.

As an Innovation newsletter subscriber, you've already earned 5 points, and if you've joined our Yammer community, you've already earned 5 more. Click here to find out how you can earn additional points and see how you stack up against your peers.
HISTORY
Lake Chautauqua Bridge

In a joint venture with Raymond International, Kiewit's Eastern Marine District was awarded a $19 million contract to construct 1.35 miles of bridge approaches and substructures across Lake Chautauqua, in southwestern New York as part of the 284-mile long Southern Tier Expressway. Raymond International had been awarded a contract in 1973, but a federal court injunction halted construction due to environmental issues. NYSDOT assured authorities that proper ecological precautions would be taken during construction on the lake and surrounding watershed.

In late 1978 and early 1979, personnel and equipment were mobilized to start marine operations, which included the construction of 20 piers on precast concrete cylinder piles. Environmental concerns and the unique design of the bridge substructure made it necessary to pour the footings using a dewatered form. This led to the design and application of an innovative construction method to build the pier footings in four sequential phases.  

The first phase consisted of pouring a precast element on a submersible barge used as a working table. The precast element was an 11-inch thick reinforced concrete slab, 10-inches wider and longer than the plan's footing dimension. The slab had 45-inch diameter corrugated metal pipes embedded vertically to allow for the passage of 36-inch tubular concrete pilings. After the slab was poured, Robishaw flexifloat units were placed around the perimeter on the outer 5 inches of the slab and interlocked using neoprene to provide a watertight seal. The working table was then towed to deep water and submerged to float the form system free.

Phase two was complete once the floating form system was placed in its proper location and the 36-inch diameter tubular concrete piling was driven using a Manitowoc 4000W Ringer and Conmaco 300 hammer mounted on a flexifloat barge.

Phase three consisted of several operations starting with the placing of inner tubes, which were inflated with water, and a 6-inch layer of sealing grout tremied in the opening, using the tubes as a soffit. Supporting friction collars were then placed on the piles to resist uplift, and after a short cure period, the footing form was dewatered. Minor leaks were plugged, and structural grout was placed to ensure a bond between the piles and the soffit slab, allowing most of the supporting hardware to be removed. A 6-foot pile plug was poured in the top of each pile, and reinforcing steel was set in the footing. 

The formwork for a starter wall, which allowed later column or wall pours to be accomplished above water, was set in place with precast channel markers which outlined the location of the submerged footing. After footing concrete was barged in buckets to the pier location and poured, the starter wall formwork and form floats were stripped and returned to shore for use on another footing.  

A crane barge was used to complete the fourth and final phase, erecting the formwork and making subsequent pours above the water for either columns and caps or walls.  

Variations of the "floating concrete box" system were reportedly used in Canada and were found to be considerably faster than conventional sheet-pile cofferdam methods. Compared to traditional methods, the approach caused less underwater soil disturbance, minimizing environmental impact.
Do you enjoy the monthly innovation history article? If so, you're going to love the newly redesigned Innovation History timeline. You'll find every history article we've ever published organized by decade in our new "digital-first" format. That means less text and more pictures and videos whenever possible.
KIEWIT INNOVATION
Duct Tie-In Adapter

The MECT Metro Blue Line project team in Los Angeles developed tie-in adaptors to transition to standard 4-inch PVC conduits to optimize installation work and help reduce cost.
Roller Screed for Embedded Track

The track team building the ION rapid transit system in Waterloo, Canada worked with a local metal shop to manufacture several different types of roller tubes that could be used to screed different types of track cross-sections.
Pressure-Washing Truck

Members of the Kiewit Northwest District came up with a more efficient way to pressure wash several widened joints prior to compression sealing on the Kapalama Container Terminal project in Hawaii. 
Crane Transportation and Assembly for Wind Farms

While supporting work at several wind farms, the Kiewit Equipment Group (KEG) found an innovative way to save schedule time and logistic costs moving large cranes used to assemble wind turbines.
New Kiewit Innovation Swag

If you have innovation points to spend, you find new options on the incentive rewards page including a 14-ounce mug (10 points) and a new full-zip three-layer knit jacket (50 points). We've also reduced the cost of the light rain jacket to 40 points. Send an email to innovate@kiewit.com to redeem points you've earned.
Tell us about your Kiewit innovation and we'll help you get it documented and published. Click here to get started. When we publish your report you'll earn 50 points you can spend on one or more items listed here.
KIEWIT NEWS
Annual Meeting

Did you miss one of the all-company Annual Meeting virtual sessions? Catch up here.
2022 PCI Design Award Winner

Congratulations to the Arlington Memorial Bridge team for winning the 2022 PCI Design Award.

P2P - GEP Next Gen Interface

If you missed the live event on the new user interface, enhancements, and training opportunities, click here for links to the recordingpresentation, and Q&A, and to signup for training from the Customer Success team.
Portfolio Optimization

The Technology Group had a lofty goal of $5 million in software savings for 2021.  Find out how they did (jump to the 4:00 minute mark to see the numbers) and what their plan is to continue to optimize the Kiewit software portfolio.
Online Tax Statements

Accessing your year-end online tax statements is faster and easier than waiting for a mailed copy. Kiewit offers single sign-on for U.S. staff employees to access W-2/1095-C forms, and for Canadian staff employees to access T4/RL-1 forms.
INDUSTRY NEWS
Indiana DOT Carbon Nanofiber UHPC Bridge Replacement

Indiana DOT completed its first all-precast bridge replacement using carbon nanofiber ultra-high-performance concrete (UHPC) known as Next Generation UHPC 2.0. While traditional concrete has a compression strength of 4,000 to 6,000 psi, UHPC 2.0 can reach 10,000 psi in 10 hours and 15,000 psi in 24 hours.
NPCA's Jointed Precast Concrete Pavement Web Explorer

The National Precast Concrete Association has launched an interactive map that shows completed or in-process jointed precast concrete pavement (JCPC) projects in North America. 
Swift Gates

Kier is trialing a new gate system on a road job in the U.K. which is designed to replace rows of cones to taper off lanes and protect highways workers.
Concrete Botox

Metrail Construction is injecting resin to stabilize concrete on a highway project in the U.K. The technique, used to stabilize rail tunnels including the London Underground, is a first on England's road network.
Robotic Roadworks and Excavation System (RRES)

With a fully articulated robotic arm on a battery-powered platform, the RRES can perform gas line repairs beneath a paved road. Working through a keyhole cut in the pavement with only a single lane of traffic disruption, the RRES condenses down an operation that would normally take a small crew of workers.
Intelligent Robotic Excavator

Zoomlion Heavy Industry Science & Technology Co. has launched what it calls the first collaborative intelligent robotic excavator. It uses artificial intelligence and other advanced technologies to drive to a target site and work autonomously. 
Want more? Click here to browse other interesting articles and videos about new technology trends from the last 30 days.

Do you like receiving this newsletter?
Yes - keep me subscribed
No - please unsubscribe me