495 NEXT LANE CLOSURES & TRAFFIC CHANGES

January 24 - 31, 2025

The following construction-related lane closures and traffic changes are planned in the I-495 Express Lanes Northern Extension (495 NEXT) project corridor. Travelers may encounter delays in this area. All work is subject to change based on weather and other factors.


Visit 511virginia.org for information on work zones and lane closures.

495 NEXT Project Area Map

495 NEXT Project Area Map

Upcoming Highlights


  • Big Beam Weekend beginning at 9 p.m. on Friday, January 24, until as late as 5 a.m. on Monday, January 27 – Major traffic impacts from lane closures and traffic shifts on northbound I-495 near Tysons and ramp closures with detours at the I-495 and Dulles Corridor interchange
  • I-495 North and South – Daytime single lane closures and nighttime multi-lane closures with stoppages
  • George Washington Memorial Parkway Daytime single mobile lane closures
  • Live Oak Drive, Balls Hill Road, Old Dominion Drive and Lewinsville Road – Daytime flagging operations
  • Georgetown Pike – Daytime single lane closures
  • Dulles Toll Road and Dulles Airport Access Highway – Nighttime ramp closure with detour

Bridge Girders to be Installed Over I-495 North in Virginia Over Big Beam Weekend: January 24-27, 2025


On northbound I-495 in Virginia, 6 travel lanes (4 general purpose and 2 express) will be reduced to 2 lanes for about 1 mile near Tysons for the entire weekend, beginning at 9 p.m. on Friday, Jan. 24 through 5 a.m. on Monday, Jan. 27. The 2 travel lanes will operate as general-purpose lanes in this area, and vehicles will not be tolled. All lanes on southbound I-495 in Virginia will remain open.


Click here for more information about the Big Beam Weekend.

Lane Closures by Location

I-495 (CAPITAL BELTWAY)

Dates

Time

Direction

Description

Limits

Reason

1/24/25 – 1/27/25

(F-M)

Continuous from 9 p.m. on Friday 1/24/25 to 5 a.m. on Monday 1/27/25

Northbound Express Lanes

Traffic diversion: Express lanes diverted into general purpose lanes


More information

Traffic diversion: Express lanes diverted into general purpose lanes

Big Beam Weekend: major girder installation

1/24/25 – 1/27/25

(F-M)

Continuous from 9 p.m. on Friday 1/24/25 to 5 a.m. on Monday 1/27/25

Northbound General Purpose and Express Lanes

Lane reduction and traffic diversion: 6 total lanes reduced to 2 lanes and diverted to express lanes


More information

North of Route 123 to north of Dulles Toll Road/Route 267

Big Beam Weekend: major girder installation

1/27/25 & 1/30/25

(M-Th)

10 a.m. – 3 p.m.

Northbound

Single lane closure

Dulles Toll Road to George Washington Memorial Parkway

Road widening work

1/27/25 & 1/30/25

(M-Th)

9:30 a.m. – 2:30 p.m.

Southbound

Single lane closure

George Washington Memorial Parkway to Dulles Toll Road

Road widening work

1/27/25 & 1/30/25

(M-Th)

9:30 p.m. – 5 a.m.

Northbound

Multi-lane closures with periodic stoppages after midnight

Dulles Toll Road to George Washington Memorial Parkway

Bridge work

1/27/25 – 1/30/25

(M-Th)

9:30 p.m. – 5 a.m.

Southbound

Multi-lane closures

Dulles Toll Road to George Washington Memorial Parkway

Barrier work

1/27/25 & 1/28/25

(M & Tu)

9:30 p.m. – 5 a.m.

Southbound Collector-Distributor Road for Exits 43 & 44

Single lane closure

George Washington Memorial Parkway to Georgetown Pike

Bridge work

GEORGE WASHINGTON MEMORIAL PARKWAY

Dates

Time

Direction

Description

Limits

Reason

1/28/25 – 1/30/25

(Tu-Th)

9:30 a.m. – 3 p.m.

Southbound / Eastbound

Single mobile lane closure

Bridge over I-495 to Turkey Run

Survey work

LIVE OAK DRIVE

Dates

Time

Direction

Description

Limits

Reason

1/27/25 & 1/28/25

(M & Tu)

9 a.m. – 3:30 p.m.

Alternating

Single lane closure with flagging operation to alternate traffic

Langley Swim and Tennis Club to Green Oak Drive

Barrier work

1/29/25 – 1/31/25

(W-F)

7 a.m. – 7 p.m.

Alternating

Single lane closure with flagging operation to alternate traffic

Langley Swim and Tennis Club to Green Oak Drive

Barrier work

BALLS HILL ROAD

Dates

Time

Direction

Description

Limits

Reason

1/27/25 – 1/30/25

(M-Th)

9 a.m. – 3:30 p.m.

Alternating

Single lane closure with flagging operation to alternate traffic

Benjamin Street to Live Oak Drive

Underdrain work

1/31/25

(F)

9 a.m. – 2 p.m.

Alternating

Single lane closure with flagging operation to alternate traffic

Benjamin Street to Live Oak Drive

Underdrain work

GEORGETOWN PIKE

Dates

Time

Direction

Description

Limits

Reason

1/27/25 – 1/30/25

(M-Th)

9:30 a.m. – 3 p.m.

Eastbound

Single right lane closure

Linganore Drive to Balls Hill Road

Pile driving work

OLD DOMINION DRIVE

Dates

Time

Direction

Description

Limits

Reason

1/28/25 – 1/30/25

(Tu-Th)

9:30 a.m. – 3 p.m.

Alternating

Single lane closure with flagging operation to alternate traffic

Dulany Drive to Dominion Court

Paving work

1/31/25

(F)

9:30 a.m. – 2 p.m.

Alternating

Single lane closure with flagging operation to alternate traffic

Dulany Drive to Dominion Court

Paving work

LEWINSVILLE ROAD

Dates

Time

Direction

Description

Limits

Reason

1/27/25 – 1/30/25

(M-Th)

9:30 a.m. – 3 p.m.

Alternating

Single lane closure with flagging operation to alternate traffic

Snow Meadow Lane to Scotts Run Road

Sidewalk work

1/31/25

(F)

9:30 a.m. – 2 p.m.

Alternating

Single lane closure with flagging operation to alternate traffic

Snow Meadow Lane to Scotts Run Road

Sidewalk work

DULLES TOLL ROAD (DTR) & DULLES AIRPORT ACCESS HIGHWAY (DAAH)

Dates

Time

Direction

Description

Limits

Reason

1/24/25 – 1/27/25

(F-M)

Continuous from 9 p.m. on Friday 1/24/25 to 5 a.m. on Monday 1/27/25

Eastbound DTR to northbound I-495

Ramp closure and detour


More information

Exit 18B: detoured to southbound I-495 to northbound Route 123

Big Beam Weekend: major girder installation

1/24/25 – 1/27/25

(F-M)

Continuous from 9 p.m. on Friday 1/24/25 to 5 a.m. on Monday 1/27/25

Eastbound DAAH to northbound I-495

Ramp closure and detour


More information

Exit 18B: detoured to southbound Route 123

Big Beam Weekend: major girder installation

1/24/25 – 1/27/25

(F-M)

Continuous from 9 p.m. on Friday 1/24/25 to 5 a.m. on Monday 1/27/25

Westbound DTR

Road closure and detour


More information

Westbound DTR under I-495

Big Beam Weekend: major girder installation

1/27/25 – 1/30/25

(M-Th)

9:30 p.m. – 5 a.m.

Eastbound DTR/DAAH

Ramp closure with detour


More information

Exit 18B, eastbound DTR/DAAH to northbound I-495

Bridge work

Traffic Changes

New Exit Ramp for I-495 North Exit to Dulles Toll Road


Reminder: Motorists traveling on northbound I-495 heading for westbound Dulles Toll Road must take a new, earlier exit. The new exit ramp is located about one-third of a mile ahead of the old, closed Exit 45. To facilitate this new traffic pattern, I-495 has been reduced from four to three lanes for approximately one-half mile near the Dulles Corridor interchange.

George Washington Memorial Parkway West at I-495


Reminder: The ramp from westbound George Washington Memorial Parkway to southbound I-495 (Capital Beltway) was reduced from two lanes to one lane to make room for a construction vehicle haul route that will be separated from traffic by a physical barrier. This traffic change will be in effect throughout construction on the 495 NEXT project.

Project Background

The I-495 Express Lanes Northern Extension (495 NEXT) project will extend the existing 495 Express Lanes north by two-and-a-half miles from the Dulles Corridor interchange to the George Washington Memorial Parkway interchange in the vicinity of the American Legion Bridge. The project will provide new and improved connections at the Dulles Corridor and George Washington Memorial Parkway.


Other project benefits include four miles of new bicycle and pedestrian connections including a shared-use path parallel to I-495 from Lewinsville Road to near Live Oak Drive, replacement or rehabilitation of seven bridges with pedestrian accommodations, replacement of nine existing noise walls and construction of a new noise wall, environmental improvements introducing stormwater management facilities and funding of restoration at Scott's Run stream, and dedicated funding to support transit improvements in the corridor including new bus service over the American Legion Bridge. 

 

495 NEXT is a public-private partnership project between the Commonwealth of Virginia and Transurban, operator of the existing 495 Express Lanes. Lane Construction is the design-build contractor for the project. The new extended lanes are scheduled to open in 2025. 

Learn More About the Project


Check out 495next.vdot.virginia.gov for additional information.


Sign up to receive project email updates.



Laptop showing 495 NEXT website

Questions?

Email: 495NorthernExtension@vdot.virginia.gov

Call: Construction Inquiry Line, 703-592-6430

Virginia Department of Transportation, Michelle Holland, 703-586-0487

Transurban, Amanda Allen, 571-249-8784

Lane Construction, John Undeland, 703-785-3461