495 NEXT LANE CLOSURES & TRAFFIC CHANGES

February 14 - 23, 2025

The following construction-related lane closures and traffic changes are planned in the I-495 Express Lanes Northern Extension (495 NEXT) project corridor. Travelers may encounter delays in this area. All work is subject to change based on weather and other factors.


Visit 511virginia.org for information on work zones and lane closures.

495 NEXT Project Area Map

495 NEXT Project Area Map

Upcoming Highlights


  • I-495 North and South – Daytime single lane closures and nighttime single and multi-lane closures with stoppages
  • I-495 North Express Lanes – Daytime single lane closures
  • Live Oak Drive, Balls Hill Road, Old Dominion Drive and Lewinsville Road – Daytime flagging operations
  • Georgetown Pike – Daytime ramp narrowing and nighttime ramp closure with detour
  • Dulles Toll Road and Dulles Airport Access Highway – Daytime single lane closure and nighttime ramp closure with detour

Lane Closures by Location

I-495 (CAPITAL BELTWAY)

Dates

Time

Direction

Description

Limits

Reason

2/14/25

(F)

10 p.m. – 8 a.m.

Southbound

Single right lane closure

George Washington Memorial Parkway to Old Dominion Drive

Excavation work

2/14/25

(F)

9:30 p.m. – 5 a.m.

Northbound


Multi-lane closures with periodic


More information

Dulles Toll Road to George Washington Memorial Parkway

Bridge work

2/17/25 – 2/19/25

(M-W)

9 a.m. – 3 p.m.

Northbound & Southbound

Mobile shoulder closure


More information

Cabin John Parkway to the American Legion Bridge (in Maryland)

Sign installation and barrier work

2/17/25 – 2/20/25

(M-Th)

10 a.m. – 3 p.m.

Northbound

Single lane closure

Dulles Toll Road to George Washington Memorial Parkway

Road widening work

2/17/25 – 2/20/25

(M-Th)

9:30 a.m. – 2:30 p.m.

Southbound

Single lane closure

George Washington Memorial Parkway to Dulles Toll Road

Road widening work

2/17/25 – 2/20/25

(M-Th)

10 a.m. – 3 p.m.

Northbound Express Lanes

Single left lane closure

Dulles Toll Road to Lewinsville Road express lanes exit

Pole installation

2/20/25

(Th)

9 a.m. – 3 p.m.

Southbound

Single right lane closure


More information

Cabin John Parkway to the American Legion Bridge (in Maryland)

Survey and overhead sign structure work

2/21/25

(F)

10 a.m. – 12 p.m.

Northbound & Southbound

Single mobile lane closure

Dulles Toll Road to George Washington Memorial Parkway

Road maintenance work

2/17/25 – 2/22/25

(M-Sat)

9:30 p.m. – 5 a.m.

Northbound

Multi-lane closures with periodic stoppages after midnight


More information

Dulles Toll Road to George Washington Memorial Parkway

Bridge work

2/17/25 – 2/22/25

(M-Sat)

9:30 p.m. – 5 a.m.

Southbound

Multi-lane closures with periodic stoppages after midnight

George Washington Memorial Parkway to Dulles Toll Road

Old Dominion Drive Bridge demolition and road work

2/19/25

(W)

10 p.m. – 5 a.m.

Southbound

Single right lane closure


More information

Cabin John Parkway to the American Legion Bridge (in Maryland)

Barrier installation work

2/20/25

(Th)

10 p.m. – 5 a.m.

Southbound

Single left lane closure


More information

Cabin John Parkway to the American Legion Bridge (in Maryland)

Barrier installation work

2/23/25

(Sun)

10 p.m. – 5 a.m.

Northbound

Single left lane closure


More information

Cabin John Parkway to the American Legion Bridge (in Maryland)

Barrier installation work

LIVE OAK DRIVE

Dates

Time

Direction

Description

Limits

Reason

2/17/25 – 2/20/25

(M-Th)

9 a.m. – 3:30 p.m.

Alternating

Single lane closure with flagging operation to alternate traffic

Langley Swim and Tennis Club to Green Oak Drive

Barrier work

2/21/25

(F)

9 a.m. – 2 p.m.

Alternating

Single lane closure with flagging operation to alternate traffic

Langley Swim and Tennis Club to Green Oak Drive

Barrier work

BALLS HILL ROAD

Dates

Time

Direction

Description

Limits

Reason

2/17/25 – 2/20/25

(M-Th)

9 a.m. – 3:30 p.m.

Alternating

Single lane closure with flagging operation to alternate traffic

Benjamin Street to Live Oak Drive

Underdrain work

2/21/25

(F)

9 a.m. – 2 p.m.

Alternating

Single lane closure with flagging operation to alternate traffic

Benjamin Street to Live Oak Drive

Underdrain work

GEORGETOWN PIKE INTERCHANGE

Dates

Time

Direction

Description

Limits

Reason

2/16/25

(Sun)

10 p.m. – 5 a.m.

East- and Westbound to Southbound

Ramp closure with detour


More information

East- and Westbound Georgetown Pike to Southbound I-495

Noise wall work

2/17/25 – 2/20/25

(M-Th)

9:30 a.m. – 3 p.m.

Southbound to East- and Westbound

Ramp narrowing

Southbound I-495 to East- and Westbound Georgetown Pike

Underdrain inspection work

2/21/25

(F)

9:30 a.m. – 2 p.m.

Southbound to East- and Westbound

Ramp narrowing

Southbound I-495 to East- and Westbound Georgetown Pike

Underdrain inspection work

2/17/25 – 2/23/25

(M-Sun)

10 p.m. – 5 a.m.

East- and Westbound to Southbound

Ramp closure with detour


More information

East- and Westbound Georgetown Pike to Southbound I-495

Noise wall work

OLD DOMINION DRIVE

Dates

Time

Direction

Description

Limits

Reason

2/17/25 – 2/20/25

(M-Th)

9:30 a.m. – 3 p.m.

Alternating

Single lane closure with flagging operation to alternate traffic

Dulany Drive to Dominion Court

Cabling and paving work

2/21/25

(F)

9:30 a.m. – 2 p.m.

Alternating

Single lane closure with flagging operation to alternate traffic

Dulany Drive to Dominion Court

Paving work

LEWINSVILLE ROAD

Dates

Time

Direction

Description

Limits

Reason

2/17/25 – 2/20/25

(M-Th)

9:30 a.m. – 3 p.m.

Alternating

Single lane closure with flagging operation to alternate traffic

Snow Meadow Lane to Scotts Run Road

Drainage work

2/21/25

(F)

9:30 a.m. – 2 p.m.

Alternating

Single lane closure with flagging operation to alternate traffic

Snow Meadow Lane to Scotts Run Road

Drainage work

DULLES TOLL ROAD (DTR) & DULLES AIRPORT ACCESS HIGHWAY (DAAH)

Dates

Time

Direction

Description

Limits

Reason

2/18/25

(Tue)

9 a.m. – 3 p.m.

Westbound DTR

Left lane closure

I-495 interchange to Spring Hill Road

Overhead sign work

2/17/25 – 2/22/25

(M-Sat)

9:30 p.m. – 5 a.m.

Eastbound DTR/DAAH

Ramp closure with detour


More information

Exit 18B, eastbound DTR/DAAH to northbound I-495

Bridge work

Traffic Changes

New Exit Ramp for I-495 North Exit to Dulles Toll Road


Reminder: Motorists traveling on northbound I-495 heading for westbound Dulles Toll Road must take a new, earlier exit. The new exit ramp is located about one-third of a mile ahead of the old, closed Exit 45. To facilitate this new traffic pattern, I-495 has been reduced from four to three lanes for approximately one-half mile near the Dulles Corridor interchange.

George Washington Memorial Parkway West at I-495


Reminder: The ramp from westbound George Washington Memorial Parkway to southbound I-495 (Capital Beltway) was reduced from two lanes to one lane to make room for a construction vehicle haul route that will be separated from traffic by a physical barrier. This traffic change will be in effect throughout construction on the 495 NEXT project.

Project Background

The I-495 Express Lanes Northern Extension (495 NEXT) project will extend the existing 495 Express Lanes north by two-and-a-half miles from the Dulles Corridor interchange to the George Washington Memorial Parkway interchange in the vicinity of the American Legion Bridge. The project will provide new and improved connections at the Dulles Corridor and George Washington Memorial Parkway.


Other project benefits include four miles of new bicycle and pedestrian connections including a shared-use path parallel to I-495 from Lewinsville Road to near Live Oak Drive, replacement or rehabilitation of seven bridges with pedestrian accommodations, replacement of nine existing noise walls and construction of a new noise wall, environmental improvements introducing stormwater management facilities and funding of restoration at Scott's Run stream, and dedicated funding to support transit improvements in the corridor including new bus service over the American Legion Bridge. 

 

495 NEXT is a public-private partnership project between the Commonwealth of Virginia and Transurban, operator of the existing 495 Express Lanes. Lane Construction is the design-build contractor for the project. The new extended lanes are scheduled to open in 2025. 

Learn More About the Project


Check out 495next.vdot.virginia.gov for additional information.


Sign up to receive project email updates.



Laptop showing 495 NEXT website

Questions?

Email: 495NorthernExtension@vdot.virginia.gov

Call: Construction Inquiry Line, 703-592-6430

Virginia Department of Transportation, Michelle Holland, 703-586-0487

Transurban, Mike McGurk, 571-421-5364

Lane Construction, John Undeland, 703-785-3461

Facebook  Instagram  X  YouTube