I-495 (CAPITAL BELTWAY)
I-495 North
Monday, September 11, through Thursday, September 14, 10 a.m. to 3 p.m.
Single right lane closures on northbound I-495 between Lewinsville Road and George Washington Memorial Parkway for drainage, embankment, and bridge work.
Monday, September 11, through Friday, September 15, 10 a.m. to 3 p.m.
Alternating single mobile lane closures on northbound I-495 throughout the project corridor for traffic management.
Monday, September 11, through Friday, September 15, 9:30 p.m. to 5 a.m.
Multi-lane mobile lane closures on northbound I-495 at Georgetown Pike for surveying and boring work.
Monday, September 11, through Friday, September 15, 9:30 p.m. to 5 a.m.
Alternating single mobile lane closures on northbound I-495 throughout the project corridor as needed for maintenance work and materials delivery.
I-495 South
Monday, September 11, through Thursday, September 14, 9:30 a.m. to 2:30 p.m.
Single right lane closures on southbound I-495 between Georgetown Pike and Dulles Toll Road for drainage, embankment, and bridge work.
Monday, September 11, through Friday, September 15, 9:30 a.m. to 2:30 p.m.
Alternating single mobile lane closures on southbound I-495 throughout the project corridor for traffic management.
Monday, September 11, through Friday, September 15, 9:30 p.m. to 5 a.m.
Multi-lane mobile lane closures on southbound I-495 at Georgetown Pike for surveying and boring work.
Monday, September 11, through Friday, September 15, 9:30 p.m. to 5 a.m.
Alternating single mobile lane closures on southbound I-495 throughout the project corridor as needed for maintenance work and materials delivery.
|