We’re scheduled to install new lane shifts this weekend on I-95 South and Route 146 North at the I-95 North Viaduct in Providence.
|
|
|
Bridge Group 32, Cranston/Providence
|
|
|
Broad Street Regeneration, Pawtucket/Central Falls/Cumberland
|
Daytime center island installations continue on Exchange Street and Goff Avenue in Pawtucket. Next week, we are also planning sidewalk installations on Broad Street at Cross Street, Fales Street, Hunt Street and High Street in Central Falls, and demolition of existing sidewalks on Mendon Road at Broad Street in Cumberland. Get lane closure and project information here.
|
|
|
Henderson Bridge, East Providence/Providence
|
Prep work for the last of the temporary traffic signals on North Brow Street in East Providence, continued demolition of the westbound bridge deck, sidewalks and parapets, and final excavation for the closed Massasoit Avenue on-ramp to the westbound bridge are the scheduled focus of our weekday operations next week.
|
|
|
I-95 North Viaduct, Providence
|
The new lane shifts for this ongoing project, mentioned above, should be in place effective Sunday morning for about a year. Next week, overnight demolition of the old I-95 South bridge is anticipated on I-95 North Sunday-Thursday nights as is debris fence and barrier installations on I-95 South. We plan to continue striping all ramps within the Exit 22 interchange Tuesday-Thursday nights, and to install barrier on Route 146 North, Monday night. During the day, we will continue bridge work on Charles and Ashburton streets and ask that motorists remain vigilant through all work zones.
|
|
|
Louisquisset Pike Bridge, Lincoln
|
A left lane closure is scheduled next week on both sides of Route 116 under Route 146 as we continue to build the center pier for the southbound bridge. Wall and drainage work are also planned at the abutment areas.
|
|
|
Manville Bridge, Cumberland/Lincoln
|
|
|
Route 5 Reconstruction, Cranston/Warwick
|
|
|
Route 6/10 Interchange Reconstruction, Providence
|
Work next week for this project requires weekday alternating lane closures on both directions of Route 10. We plan to continue storm drainage installation along the Route 10 median, demolish the Westminster Street Bridge superstructure and form its east abutment foundation, form a concrete barrier on the recently poured and cured section of the new flyover bridge deck, and place steel reinforcement on the south span at the Broadway Bridge.
|
|