LaSalle Rd reopens in both directions.

Trees will be installed next week!


  • Paving of the southbound travel lane has been substantially completed. LaSalle Road will be fully reopened to two-way traffic by the end of the day on Friday, October 10th.


  • Paving of a temporary top course along the western curbline was installed on Monday, October 13th. Marking of the parking stalls will follow soon after.


  • Sidewalk improvements are continuing along the east side of LaSalle Road. The work includes installing soil cells, street lighting, grading sidewalks, and pouring new concrete.


  • Planting of new trees is expected to begin around the end of next week. 